Among the various functions provided by progress tracking that simplify data entry and analysis which function allows you to go the master data display for objects that are underlined?
Please choose the correct answer.
Response:
Which function allows you to check consistency of the dates within the project structure with or without taking activities into account?
Please choose the correct answer.
Response:
If the available user-definable fields do not satisfy your requirement, you have an option to develop additional fields for which of the following.
There are 2 correct answers to this question.
Response:
Which variant defines the valuation procedure for materials, internal activities, external activities, and business processes?
Please choose the correct answer.
Response:
Based on which of the following the checking control function determines whether an order type will be checked and if so, which checking rules should be used?
Please choose the correct answer.
Response:
Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity?
Please choose the correct answer.
Response:
Capacity planning board
Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis?
Please choose the correct answer.
Response:
Which parameters determine if the network header or network activities are cost objects?
There are 2 correct answers to this question.
Response:
What are the different procurement types you can choose between if you choose direct procurement with item category N?
There are 2 correct answers to this question.
Response:
What do you call a closed sequence of relationships and activities where you start from an activity and end up back at the same activity, by way of relationships?
Please choose the correct answer.
Response: