Identify the missing word in the following sentence:

Stakeholder engagement is defined as a way of exercising influence and achieving positive [?] through effective management of relationships.

A.

responses

B.

outcomes

C.

benefits

D.

engagements

Which is a purpose of the ‘plan progressive delivery’ process?

A.

It monitors progress and takes corrective action to keep the programme on track

B.

It structures the projects and other work into tranches to achieve the required capabilities

C.

It enables the organization(s) involved to understand the programme vision

D.

It incorporates the planning and management of the transition from old to new ways of working

Which process produces an understanding of the gap between the current state and future state of the organization before detailed structuring of the programme is started?

A.

Plan progressive delivery

B.

Design the outcomes

C.

Identify the programme

D.

Deliver the capabilities

How does the ‘organization’ theme apply the ‘deal with ambiguity’ principle?

A.

By adapting structures and roles over time to align with business operations

B.

By defining the risk appetite and enabling transparency of risks being taken

C.

By overseeing the development of the required number of resources and their skills

D.

By facilitating interactions between organizational units and stakeholders

Which activity BEST achieves the ‘deploy diverse skills’ principle?

A.

Supporting stakeholders to have the information they need to understand priorities

B.

Allocating the right resources to assurance activities, balancing independence, knowledge and cost

C.

Facilitating information sharing, enabling transparent, evidence-based decision-making

D.

Planning delivery appropriately to achieve the future state and required outcomes of benefit

Which describes an external factor that influences a programme?

A.

The lifecycle and delivery mode selected for each project

B.

The defined strategy for capturing and sharing knowledge

C.

Changes in the behaviours of an organization's competitors

D.

Existing ways of working embedded in business as usual activities

Identify the missing word in the following sentence:

A dis-benefit is defined as a measurable decline resulting from an outcome perceived as negative by the investing organization(s) and which detracts from one or more organizational [?].

A.

benefits

B.

outcomes

C.

objectives

D.

capabilities

How is the accountability success factor achieved?

A.

By objectively assessing based on evidence

B.

By ensuring work is conducted at the right time

C.

By maximising the impact and minimizing effort

D.

By reporting findings through governance boards

Which term is used to describe the amount of risk the investing organization(s) is willing to accept in pursuing the benefits of the programme?

A.

Risk universe

B.

Benefits map

C.

Risk appetite

D.

Benefit profile

Which BEST describes the ‘align with priorities’ principle?

A.

It uses a mix of internal and external resources to achieve outcomes of benefit

B.

It ensures that a programme adapts to changing, and often conflicting, organizational objectives

C.

It enables different parts of an organization to work together to transform and implement new policy

D.

It enables informed decisions based on an understanding of the uncertain nature of a programme