Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.

2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.

A.

a solution should be designed for

B.

an issue should be created for

C.

the agreed actions should be recorded for

D.

the chair will approve the solution to

Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

A.

Specify the desired result

B.

Provide the resources and skills to deliver the desired result

C.

Ensure the technical integrity of a project

D.

Develop a project's products

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

A.

Change

B.

Cross-functional

C.

Unique

D.

Risk

Which is NOT a purpose of the Organization theme?

A.

Define a project management team structure

B.

Define the level of tolerance for each level of the project management team

C.

Define the Project Board's responsibility for directing the project

D.

Define which role is accountable for the project's success

What is the definition of a project outcome?

A.

A measurable improvement that is perceived as an advantage by one or more stakeholders

B.

The reason for the project

C.

The result of the change derived from using the project's outputs

D.

The project's specialist products.

Which is a typical core activity within configuration management?

A.

Quality assurance

B.

Risk management

C.

Verification and audit

D.

Progress reporting

Whose approval is needed to replace a Stage Plan with an Exception Plan?

A.

Corporate or programme management

B.

Project Board

C.

Project Manager

D.

Team Manager

Which of the following statements about customer's quality expectations and acceptance criteria are true?

1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.

2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the ‘quality management technique should this occur?

A.

Gathering user inputs

B.

Accepting products

C.

Describing the quality management approach

D.

controlling quality