What is an off-specification?

A.

A new requirement

B.

A quality tolerance

C.

A type of issue

D.

A major risk

Which process covers the work done by external suppliers who may NOT be using PRINCE2?

A.

Closing a Project

B.

Managing a Stage Boundary

C.

Managing Product Delivery

D.

Directing a Project

Which is a true statement about time-driven controls?

A.

Time-driven controls are used for monitoring the progress of Work Packages and management stages

B.

Time-driven controls take place when specific events happen

C.

Time-driven controls are produced at the end of a stage

D.

An Exception Report is a time-driven control

Who should act as the communication channel between a project and corporate or programme management?

A.

Project Board

B.

Project Assurance

C.

Project Manager

D.

Project Support

What is the collective name for individuals or groups who may be affected by a project?

A.

Customers

B.

Project Support

C.

Stakeholders

D.

Team members

Which is a purpose of the Controlling a Stage process?

A.

Assign work to be done and take corrective action to ensure that the stage remains within tolerance

B.

Provide a fixed reference point at which acceptance for the project product is confirmed

C.

Enable the Project Board to be provided with sufficient information to authorize the next stage

D.

Enable the organization to understand the work that needs to be done to deliver the project's products

What takes place during the Closing a Project process?

A.

The post-project benefits reviews are performed

B.

Ownership of the project's products is transferred to the customer

C.

An End Stage Report is prepared for the final stage

D.

The project closure notification is reviewed and approved

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

A.

Directing a Project

B.

Managing a Stage Boundary

C.

Controlling a Stage

D.

Starting up a Project

Which product documents the information needed to demonstrate continued business justification?

A.

Business Case

B.

Communication Management Strategy

C.

Project Product Description

D.

Quality Management Strategy

Which is an objective of the Initiating a Project process?

A.

Develop the corporate quality management system as part of the Project Initiation Documentation

B.

Prepare the plans for the subsequent stages

C.

Summarize how the organization's project management method will be tailored for the project

D.

Request authority from corporate management to deliver the project