Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exc65

If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?

A.

Appointing the project board and producing the project brief

B.

Planning the initiation stage and appointing the project manager

C.

Producing the additional role descriptions and validating the project product description

D.

Verifying the project approach and capturing previous lessons

What does qualitative analysis of a risk assess, as a minimum?

A.

How soon each risk might occur

B.

The fallback plan for each risk

C.

The likelihood and the effect of each risk on objectives

D.

The speed with which the effect of each risk will be felt

In which process should the specified quality methods he used to/prove that a product meets its quality criteria?

A.

Managing product delivery

B.

controlling a stage

C.

Managing a stage boundary

D.

closing a project

The team manager has organized a workshop with project stakeholders to define the detailed requirements for a number of outputs.

Which principle is being applied by the team manager as part of the 'people’ element when holding this workshop?

A.

Focus on products

B.

Tailor to suit the project

C.

Define roles, responsibilities and relationships

D.

Ensure continued business justification

Which is NOT one of the PRINCE2 integrated elements?

A.

Tailoring PRINCE2 to the project environment

B.

The processes

C.

The products

D.

The themes

Which is an objective of the Managing Product Delivery process?

A.

Sign-off completed Work Packages

B.

Ensure the Business Case is kept under review

C.

Report progress to the Project Board

D.

Ensure that work on products is authorized and agreed with the team

Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.

A.

Avoid

B.

Reduce

C.

Share

D.

Transfer

Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

A.

a corporate

B.

a temporary

C.

an external

D.

a technical

Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

A.

Off-specifications

B.

Follow-on action recommendations

C.

Issue Register

D.

Risk Register

Which is NOT a purpose of the Initiating a Project process?

A.

Enable a Project Board decision about the commitment of resources to a project

B.

Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved

C.

Establish solid foundations for a project

D.

Enable the Project Board to decide whether it is worthwhile to initiate a project