Which TWO statements describe a purpose of the business case?

1) To define the acceptance criteria for what the project must deliver.

2) To transfer responsibility for the work to the appropriate delivery team.

3) To document how significant risks will affect the expected project benefits.

4) To outline how and when the anticipated benefits can be measured.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Which statement explains the setting of the cost tolerance for a project in an agile context?

A.

Cost tolerance is flexed

B.

Cost tolerance can be fixed or flexed

C.

Cost tolerance can be fixed and flexed

D.

Cost tolerance is fixed

How does PRINCE2 Agile describe Scrum?

A.

Scrum is an IT method

B.

Scrum is agile and agile is Scrum

C.

Scrum is the most well-known agile framework

D.

Scrum is a project management framework

Whose interests are specifically represented by the senior supplier?

1. Those ensuring the project is value for money.

2. Those who will use the project’s products.

3. Those who will be developing the project’s products.

4. Those responsible for the project’s technical integrity.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

What is an epic?

A.

A low-level requirement

B.

A fine-grained user story

C.

A detailed feature

D.

A high-level requirement

During which process should release planning be done for the FIRST time?

A.

Initiating a project

B.

Managing a stage boundary

C.

Managing product delivery

D.

Controlling a stage

Which is an advantage of using the PRINCE2 Agile behavior ‘collaboration’?

A.

It ensures that there are no surprises

B.

It allows people to provide cover for one another

C.

It uses experimentation to expand requirements

D.

It uses learning to help improve products

Which TWO statements about the supplier subject matter expert are CORRECT?

1) They provide a wider picture of the customer view.

2) They prioritize requirements at the detailed level.

3) They should be focused on the customer.

4) They ensure that the work is compliant with project standards.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

To help with prioritization, what is MOST important when understanding the difference between scope and quality?

A.

Combining functional and non-functional requirements

B.

Creating non-functional requirements with user stories

C.

Differentiating functional from non-functional requirements

D.

Defining non-functional requirements before functional requirements