During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.

The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the ‘evaluate a work package’ activity, and why?

A.

Yes, because evaluation confirms that completed quality activities are recorded and that the current status is understood by the relevant parties

B.

Yes, because the team manager should review the work-package information, report progress for the agreed period, and notify the project manager when a tolerance is forecast to be exceeded

C.

No, because only the project manager may evaluate the status of a work package and decide what it should report

D.

No, because a forecast work-package tolerance breach should be reported directly to the project board in an exception report

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

A.

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.

No, because anticipated parking income means that no alternative should be assessed

While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.

Is this an appropriate application of the ‘plans’ practice, and why?

A.

Yes, because data from previous projects should determine the schedule without reviewing the dependencies between the products

B.

Yes, because product dependencies determine sequence, and independent work packages may be planned to run in parallel

C.

No, because work delivered by the same supplier must be scheduled sequentially and should avoid running in parallel

D.

No, because setting work-package tolerances determines the order in which products must be produced

During initiation, new information from BuildyBrick shows that additional protection of historic buildings will extend the planned duration.

Which role should the project manager consult to check that the revised plan still meets the needs of the project board and business?

A.

Business layer

B.

Team manager

C.

Project assurance

D.

Project executive

While the project mandate is being prepared, the Mayor asks the LOB Portfolio Director, acting at the business layer, to select and appoint a suitable project executive for LouisShopping.

Is this an appropriate application of the organization practice, and why?

A.

Yes, because the Mayor may delegate responsibility for appointing the project executive to any senior stakeholder involved in the project

B.

Yes, because the Portfolio Director, as the business layer representative, takes responsibility for appointing the project executive

C.

No, because it is the Mayor, as the senior elected authority, who should personally select and appoint the project executive for a project of this civic significance

D.

No, because the responsibility for commissioning and initiating projects within the LOB portfolio rests with the Head of Portfolio Office, not the Portfolio Director

While selecting the project approach, the team identifies that a traditional delivery method and the proposed use of external suppliers could make the sustainability requirements harder to achieve. The risk is recorded in the project log for consideration during initiation.

Is this an appropriate application of ‘starting up a project’, and why?

A.

Yes, because the primary purpose of assessing the project approach at this stage is to clarify the prospective obligations of the project team and each external supplier when delivering the project products

B.

Yes, because the way the project work will be delivered directly influences how the management approaches are designed, and identifying risks early helps ensure the PID accurately reflects how sustainability will be managed

C.

No, because a risk that is classified as manageable does not pose a threat to overall project viability and should be deferred for consideration during the initiation stage when more detailed planning takes place using the traditional delivery method

D.

No, because any sustainability requirements that the project must satisfy should be captured as user quality expectations in the project product description, not as risks in the project log

In stage 4, work is late because the survey and utilities teams have not shared information needed by other teams, and morale is falling. The project manager considers a short weekly coordination forum for questions and information sharing, but rejects it solely because it would take time away from delivery.

Is this an appropriate approach to leading a successful team, and why?

A.

Yes, because the primary responsibility for improving team morale and overall productivity rests with each individual team manager, not the project manager

B.

Yes, because requiring team managers to attend regular coordination meetings diverts their time away from completing their work packages, thereby risking further delays

C.

No, because the project manager should create mechanisms that strengthen coordination and relationships across the project team

D.

No, because the project manager should formally escalate the missed work package deadlines to the project board via an exception report rather than attempting to resolve the issue through coordination meetings

During the ‘initiating a project’ process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.

Is this an appropriate approach to leading successful change, and why?

A.

Yes, because the project manager is using existing stakeholder knowledge to identify affected and influential groups proactively

B.

Yes, because identifying a stakeholder guarantees that the stakeholder will support the project and its business case

C.

No, because stakeholder identification should not take place during project initiation

D.

No, because early identification of an opposing group will necessarily increase its opposition

BuildyBrick’s planning specialist suggests that the project manager should prepare stage plans only for stages 2 and 4, while BuildyBrick should prepare the stage plans for stages 3 and 5 because suppliers will deliver most of the work.

Is this an appropriate application of the plans practice, and why?

A.

Yes, because the specialist supplier should own the stage plan whenever it delivers most of the stage products, and team managers can prepare the relevant information

B.

Yes, because the project manager should prepare stage plans only for stages involving more than one supplier

C.

No, because each external supplier should prepare the complete stage plan for the stage in which it works

D.

No, because the project manager remains responsible for preparing each stage plan; team managers may prepare team plans and detailed work package information

QUALITY

Here are three items of information relating to the testing of the solar panels during stage 4.

Under which heading of the quality register (A–E) should each item be recorded?

Choose only ONE heading for each item. Each heading can be used once, more than once, or not at all.

A.

Quality method

B.

Dates

C.

Responsibilities

D.

Result

E.

Records

Item 1:

Specialist equipment will be used to verify that the energy output from the solar panels meets the applicable industry standards.

Item 2:

The solar-panel testing will be completed in week 2 of stage 4, one week after the security-system testing.

Item 3:

Testing found that one solar panel did not meet the required energy-output standard.