During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.
The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the ‘evaluate a work package’ activity, and why?
During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.
Is this an appropriate application of the business case practice, and why?
While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.
Is this an appropriate application of the ‘plans’ practice, and why?
During initiation, new information from BuildyBrick shows that additional protection of historic buildings will extend the planned duration.
Which role should the project manager consult to check that the revised plan still meets the needs of the project board and business?
While the project mandate is being prepared, the Mayor asks the LOB Portfolio Director, acting at the business layer, to select and appoint a suitable project executive for LouisShopping.
Is this an appropriate application of the organization practice, and why?
While selecting the project approach, the team identifies that a traditional delivery method and the proposed use of external suppliers could make the sustainability requirements harder to achieve. The risk is recorded in the project log for consideration during initiation.
Is this an appropriate application of ‘starting up a project’, and why?
In stage 4, work is late because the survey and utilities teams have not shared information needed by other teams, and morale is falling. The project manager considers a short weekly coordination forum for questions and information sharing, but rejects it solely because it would take time away from delivery.
Is this an appropriate approach to leading a successful team, and why?
During the ‘initiating a project’ process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.
Is this an appropriate approach to leading successful change, and why?
BuildyBrick’s planning specialist suggests that the project manager should prepare stage plans only for stages 2 and 4, while BuildyBrick should prepare the stage plans for stages 3 and 5 because suppliers will deliver most of the work.
Is this an appropriate application of the plans practice, and why?
QUALITY
Here are three items of information relating to the testing of the solar panels during stage 4.
Under which heading of the quality register (A–E) should each item be recorded?
Choose only ONE heading for each item. Each heading can be used once, more than once, or not at all.