Virginia is the project manager for her company. She has used a previous project as a basis for her current project because they are similar in nature. Virginia has adapted nearly all of the previous project plans for her current project - including the project schedule, risk register, and communications management plan. She has worked with management to update the plans to adapt them to the current project. What are the previous project management plans called in this instance?
You are the project manager for your organization. You and the project team are developing the project schedule for your current project. This project management process will create four outputs. Which of the following is an output of the Develop Schedule process?
What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?
In the project time management knowledge area, there are six processes. According to the PMBOK, which project time knowledge area will have the majority of the effort?
You are the project manager of the NHQ Project. This project has a Budget at Completion of $750,000 and is expected to take 18 months to complete. The project is supposed to be 75 percent complete, but due to some errors the project is only 60 percent complete. At this time the project has spent $465,500. Management has asked you to review the project work and report the project's SPI. What is the SPI for this project?
If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project?
Which of the following provides a method to track project progress during project execution against what was planned?
You're a project manager and you've completed your project schedule. The schedule will take 18 months to complete the project work. Throughout the schedule there are instances that the project work will require the project team members to work more than fifty hours per week. If you must adhere to a maximum of 45 hours of project work per team member, per week, what will likely happen to your project schedule as it stands right now?
You work as a project manager for BlueWell Inc. You and your project team is undergoing the decision making process for the project. You want to involve key participants to gain acceptance and commitment to make the solution work. Which of the following phases of the decision- making model defines this process of work?
Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two months, but Henry has a conflict and is already scheduled with another project manager in the organization. This is an example of which of the following?