Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?

A.

Scope baseline

B.

Organizational process assets

C.

WBS

D.

Enterprise environmental factors

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:

A.

Communications bull's eye

B.

Performance goals

C.

Earned value management goals

D.

Project exception report

Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated project schedule based on project performance. She is using the supporting schedule data, manual scheduling methods, and her project management software to perform schedule network analysis. What other tool Winnie can use to help and generate an updated project schedule?

A.

Critical path method

B.

Schedule management plan

C.

Scheduling tool

D.

Critical chain method

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?

A.

$142,000

B.

$232,000

C.

$41,750

D.

$23,750

Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedule performance index?

A.

PV/EV

B.

EV-AC

C.

EV-PV

D.

EV/PV

Gary is the project manager of the NHF project, which is a part of a program in his organization. According to the PMBOK, how will Gary provide feedback to programs and portfolios?

A.

Status meetings

B.

Push communications

C.

Regular communications

D.

Status reports and change requests

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?

A.

Cost variance report

B.

Exceptions report

C.

Performance management report

D.

Schedule variance report

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's schedule variance?

A.

-$48,654

B.

13 percent

C.

-$225,000

D.

0.98

Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project. What is the main output of the identify stakeholders process?

A.

Communications management plan

B.

Stakeholder register

C.

Requirements

D.

Stakeholder management strategy