Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated. You investigate the cause and determine that the project team is not starting their assignments early enough to finish their work on time. While the duration of the assignments may be in synchronization with the duration estimates, the completion time is causing the project schedule to slip from the baseline. What can you do to rectify this problem?

A.

Increase the duration estimates for each activity.

B.

Discipline the project team.

C.

Add management reserve.

D.

Corrective actions.

Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?

A.

Scope of statement

B.

Project charter

C.

Statement of work (SOW)

D.

WBS

George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule. What value should George report in this instance?

A.

.96

B.

-$77,800

C.

$-34,500

D.

-$13,800

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?

A.

$122,845

B.

-$51,000

C.

-$85,000

D.

Zero

You are the project manager of the JKM Project for your organization. Your project is supposed to be 60 percent complete but you are only 45 percent complete. The project has an assigned budget of $765,000 but you have already spent $365,000 to reach this point in the project due to some errors and rework. Management is pressing you on when you'll complete the project and how much the project will likely cost based on the current performance. You need to tell management what the project's current cost performance index (CPI) is. What value should you report to management based on your project's performance?

A.

$306,000

B.

.94

C.

$344,250

D.

.75

You are the project manager for the NHQ Project. Management has asked you to create a time estimate for this project although you have only just received the project charter. They would like some idea of how long the project will take based on the information in the project charter. While you are uncomfortable giving any type of estimate at this point, you work with your assigned project to create a quick time estimate. What type of estimate have you created for management?

A.

Analogous estimate

B.

Broad estimate

C.

Rough order of magnitude

D.

Expert judgment

Tom is the project manager of the HQQ Project. His project has a schedule variance of -$34,500 due to some errors early in the project. Management would like to know how Tom will respond to these variances. What action can help Tom to manage the errors in the project and to ensure that the errors would not occur again?

A.

Lesson learned documentation

B.

Risk analysis

C.

Preventive action

D.

Corrective action

John is the project manager for his organization. He has created a status dashboard for his stakeholders. What is a status dashboard?

A.

It is a report that details the current status of risks and issues.

B.

It is a software application that allows stakeholders to view the project manager's performance.

C.

It is a web-based tool to inspect the project deliverables for performance.

D.

It is a report that reflects the overall performance of scope, schedule, quality, cost, or other project performance metrics.

Your project is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked that you report on the schedule variance for your project. If your project has a BAC of $650,000 and you've spent $385,000 to date, what is the schedule variance value?

A.

-$75,500

B.

-$390,000

C.

-$487,500

D.

-$65,000

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and the organizational process assets, you will need seven other inputs to this process. Which one of the following is NOT an input to the Develop Schedule process?

A.

Resource calendars

B.

Schedule data

C.

Activity list

D.

Project scope statement