Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)

A.

Applying modern risk management techniques.

B.

Aligning to project constraints and priorities.

C.

Ensuring risk response strategies mitigate all risks.

D.

Minimizing implementation costs.

E.

Obtaining stakeholder acceptance

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.

B.

Assess and modify the project risk management plan in response to the new directive.

C.

Accept project risks since it is already within the enterprise-wide threshold.

D.

Advise that the decision could increase the risk of their portfolio exponentially.

The stakeholders of a building construction project are not comfortable with the project manager ' s handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold.

What should the risk manager do first to demonstrate this to the stakeholders?

A.

Gather other project risk historical information.

B.

Gather and reconcile project risk report data.

C.

Work with the sponsor to convince the risks are under control.

D.

Work with the team to ensure the project is in good health. 

Many customers using the global positioning system (GPS) of several automobile companies are complaining about errors due to a recent update. This update included a major technological change to mitigate emerging risks with software deployment. Upon investigation, the risk manager realized that this issue was identified as a high-risk item during risk analysis, which required secondary risk identification that was never completed.

What was missed in the risk management process that led to this incident?

A.

The identification of the business driver.

B.

The new technology ' s impact on existing controls

C.

The risk management strategy quality assurance.

D.

Project environmental factors

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.

What should the project manager have done differently?

A.

Executed the risk strategy response and recorded it in the risk register.

B.

Performed an analysis to affirm the request is valid before submitting.

C.

Informed the client and the project sponsor that the request is being submitted.

D.

Contacted the other stakeholders so they know the request is in process.

A project ' s design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.

What should the project manager have done differently?

A.

Executed the Monte Carlo sensitivity analysis prior to mobilization

B.

Added generic construction risks to the risk register before construction began

C.

Reviewed the assumptions/exclusions register in the project charter

D.

Performed risk identification exercises for the full lifecycle of the project

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

A.

Update the new risk in the risk register.

B.

Plan responses for the new risk.

C.

Passively accept the new risk.

D.

Add the new risk to the watch list.

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

A.

Ask the project sponsor if every risk in the risk register can have the same priority.

B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.

A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.

What should the risk manager do with this risk?

A.

Put the risk on the watch list.

B.

Seek guidance from subject matter experts (SMEs).

C.

Ignore this risk as it is not critical.

D.

Inform the stakeholders about this risk.

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?

A.

Avoid the risk

B.

Transfer the risk

C.

Ignore the risk

D.

Accept the risk