Month End Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)

A.

Risks that are tied to the success of the organization

B.

Risks as they apply to the organization's overall risk management philosophy and strategic ambition

C.

Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year

D.

Risks related to cost that will impact the major projects that are currently in the execution phase

E.

Risk mitigation actions that will require work from stakeholders

A project team has just initiated a large project to move an organization's headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.

What should the risk manager consider?

A.

Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.

B.

The ideal solution is to find alternate documents that provide good visibility on the environment.

C.

The risk identification process can be carried out as long as the project statement is available.

D.

Risk evaluation will be challenging without these elements as a frame of reference.

There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders, and this delays the decision-making process.

A.

Organize training sessions to create awareness around the agile values for stakeholders.

B.

Facilitate a face-to-face discussion and have stakeholders agree to shift to agile for future projects.

C.

Recommend an external facilitator as no one in the organization is able to eliminate this roadblock.

D.

Allow stakeholders to discuss without the scrum master's intervention.

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.

What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?

A.

Reinforce to the stakeholders that the risk identification was done properly during the last sprint.

B.

Highlight the importance of agreeing on the risk identification to avoid further delays.

C.

Conduct a separate meeting to show the risk identification analysis to the stakeholders.

D.

Ensure that the most knowledgeable members of the team validate risk identification processes. 

A company has implemented a policy requirement for employees to use complex passwords and update them regularly. A few employees are unable to make the changes, which increases the likelihood of cybercriminals compromising their passwords.

What should the risk manager do?

A.

Increase the residual risk monitoring.

B.

Increase the inherent risk monitoring.

C.

Reassess the inherent risk level.

D.

Reassess the residual risk level.

A risk manager is assigned to a new system deployment project with a strict contractually agreed-on schedule. One of the key risks identified is the availability of experts because many are shared on other strategic projects in the organization.

What should the risk manager do to address this situation?

A.

Implement a disciplined tracking method and report to stakeholders accordingly.

B.

Call for a project team meeting to review risk strategies and make required adjustments.

C.

Escalate the staffing topic to the sponsor and request more budget for contingencies.

D.

Revisit the project charter for scope adjustments and sign them off with the customer.

In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion.

In implementing this plan, which response should the risk manager use?

A.

Exploit

B.

Accept

C.

Share

D.

Enhance 

At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it's complete since it is such a short and simple project.

How should the risk manager respond to this comment?

A.

The risk register must only be updated if a change is approved during the project.

B.

Agree on the condition that the risk register be updated if the project environment changes.

C.

Compromise by updating the risk register at the end of each phase only.

D.

Insist on continuous review and updating of the risk register during the project.

During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables.

What should the risk manager do?

A.

Update the watchlist.

B.

Initiate a risk response when these risks occur.

C.

Address only the high-priority risk.

D.

Perform a risk urgency assessment. 

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?

A.

Product Manager

B.

Risk Action Owner

C.

Risk Owner

D.

Project Manager