A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)
A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.
How should the risk manager respond?
The stakeholders of a building construction project are not comfortable with the project manager ' s handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold.
What should the risk manager do first to demonstrate this to the stakeholders?
Many customers using the global positioning system (GPS) of several automobile companies are complaining about errors due to a recent update. This update included a major technological change to mitigate emerging risks with software deployment. Upon investigation, the risk manager realized that this issue was identified as a high-risk item during risk analysis, which required secondary risk identification that was never completed.
What was missed in the risk management process that led to this incident?
A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.
What should the project manager have done differently?
A project ' s design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.
What should the project manager have done differently?
During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.
What should the risk manager do first?
A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.
What should the risk manager do?
A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.
What should the risk manager do with this risk?
A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.
What should the project manager do?