A risk manager is assigned to a mobile network deployment project with a strict contractually agreed-on schedule. One of the key risks identified has materialized. There is insufficient staffing because critical resources are dedicated to strategic projects in the organization. The risk manager expected the resource manager to notice this, but the resource manager thought the project experts would be alerting the team during the project.
What should the risk manager do to prevent this from happening again?
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.
What should the project manager have done to avoid this?
A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.
What should the risk manager do in this case?
A project has suffered a big schedule delay and there are still some risks that are close to materializing. The project manager is concerned about communicating this risk level, because the stakeholders might suspend project funding and cancel the project.
How should the risk manager manage the risk level?
A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.
What process is this part of?
A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.
What should the risk manager do?
A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?
A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.
What should the risk manager do first?
Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.
How should the risk manager proceed?
A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.
What three artifacts should the project manager consult or review during this process? (Choose three.)