The definition of operations is a/an:

A.

organizational function performing the temporary execution of activities that produce the same product or provide repetitive service.

B.

temporary endeavor undertaken to create a unique product, service, or result.

C.

organization that provides oversight for an administrative area.

D.

organizational function performing the ongoing execution of activities that produce the same product or provide repetitive service.

Which of the following factors is lowest at the start of the project?

A.

Cost of changes

B.

Stakeholder influences

C.

Risk

D.

Uncertainty

What risk technique is used to quantify the probability and impact of risks on project objectives?

A.

Expert judgment

B.

Risk registry

C.

Risk response planning

D.

Interviewing

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

A.

Start-to-start (SS)

B.

Start-to-finish (SF)

C.

Rnish-to-finish (FF)

D.

Finish-to-start (FS)

Which is a communication method used in the Report Performance process?

A.

Expert judgment

B.

Project management methodology

C.

Stakeholder analysis

D.

Status review meetings

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

A.

Executing.

B.

Initiating,

C.

Monitoring and Controlling.

D.

Planning.

Which of the following is an input to Develop Human Resource Plan?

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

What does a CPI value greater than 1.0 indicate?

A.

Cost right at the estimated value

B.

Cost under the estimated value

C.

Cost right at the actual value

D.

Cost over the estimated value

Which activity involves ensuring that the composition of a projects configuration items is correct?

A.

Configuration Identification

B.

Configuration Status Accounting

C.

Configuration Verification and Audit

D.

Configuration Quality Assurance

Which of the following is the primary output of the Identify Risks process?

A.

Risk management plan

B.

Risk register

C.

Change requests

D.

Risk response plan

As the project progresses, which of the following is routinely collected from the project activities?

A.

Communication management activities

B.

Change requests

C.

Configuration verification and audit

D.

Work performance information

The project manager needs to review the templates in use. The templates are part of the:

A.

Enterprise environmental factors.

B.

Historical information,

C.

Organizational process assets.

D.

Corporate knowledge base.

In which Project Management Process Group is the project charter developed?

A.

Monitoring and Controlling

B.

Executing

C.

Initiating

D.

Planning

Which of the following is an output of the Monitor and Control Project Work process?

A.

Change requests

B.

Performance reports

C.

Organizational process assets

D.

Project management plan

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

A.

Resource breakdown structure

B.

Staffing management plan

C.

Project organizational chart

D.

Scope management plan