Which is the correct formula for calculating expected activity cost for three-point estimating?

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

In which Process Group are lessons learned documented?

A.

Planning

B.

Closing

C.

Executing

D.

Initiating

Which type of analysis is used as a general management technique within the Plan Procurements process?

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

In a weak matrix, the project managers role is:

A.

part-time

B.

full-time

C.

occasional

D.

unlimited

Which of the following is an output of the Distribute Information process?

A.

Project calendar

B.

Communications management plan

C.

Organizational process assets updates

D.

Project document updates

Which process occurs within the Monitoring and Controlling Process Group?

A.

Control Costs

B.

Plan Quality

C.

Perform Quantitative Risk Analysis

D.

Determine Budget

Labor, materials, equipment, and supplies are examples of:

A.

Resource attributes.

B.

Resource types.

C.

Resource categories.

D.

Resource breakdown structures (RBS).

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

A.

Product scope description

B.

Procurement statement of work

C.

Project schedule

D.

Work breakdown structure (WBS)

In Project Cost Management, which input is exclusive to the Determine Budget process?

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

A.

Monitor and Control Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Documented identification of a flaw in a project component together with a recommendation is termed a:

A.

corrective action.

B.

preventive action.

C.

non-conformance report,

D.

defect repair.

Which of the following correctly explains the term "progressive elaboration'?

A.

Changing project specifications continuously

B.

Elaborate tracking of the project progress

C.

Elaborate tracking of the project specifications with a change control system

D.

Project specifications becoming more explicit and detailed as the project progresses

Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:

A.

Conduct Procurements.

B.

Close Procurements.

C.

Administer Procurements,

D.

Plan Procurements.

An input to the Perform Quantitative Risk Analysis process is the:

A.

quality management plan.

B.

project management plan.

C.

communications management plan.

D.

schedule management plan.

What provides information regarding the ways people, teams, and organizational units behave?

A.

Organizational chart

B.

Organizational theory

C.

Organizational structure

D.

Organizational behavior