Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

An input to Close Project or Phase is:

A.

Accepted deliverables,

B.

Final products or services,

C.

Document updates,

D.

Work performance information.

Which tool or technique is used in the Perform Integrated Change Control process?

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Which document defines how a project is executed, monitored and controlled, and closed?

A.

Strategic plan

B.

Project charter

C.

Project management plan

D.

Service level agreement

Lessons learned are created and project resources are released in which Process Group?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

A.

$50

B.

$100

C.

$125

D.

$175

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

A.

Identify Risks

B.

Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses

Which process in Project Time Management includes reserve analysis as a tool or technique?

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

A.

Work performance information.

B.

Inspections and audits.

C.

Payment systems.

D.

Procurement performance reviews.

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

Which tool or technique is used to develop the human resource management plan?

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

A.

Procurement statement of work

B.

Purchase order

C.

Source selection criteria

D.

Bidder conference

The Identify Stakeholders process is found in which Process Group?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Executing

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

A.

A risk urgency assessment.

B.

The scope baseline.

C.

Work performance information.

D.

Procurement audits.