You are project manager of a project, which of the following is not your responsibility?

A.

Quality in the organization

B.

Acquiring HR resources for the project team

C.

Overall responsibility for risk on the project

D.

Al1 of the above

Which type of network diagram is also referred to Activity-on-Node (AON) diagrams?

A.

Precedence Diagramming Method (PDM)

B.

Gantt Cnart Diagram (GCD)

C.

Dependency Diagramming Method (DDM)

D.

Arrow Diagramming Method (ADM)

What are the inputs for Initiation process?

A.

Product description and Strategic plan

B.

Selection criteria

C.

Historical information

D.

Al1 of the above

Which of the following are parts of project scope management?

A.

Verify Scope

B.

Collect Requirements

C.

Control Scope

D.

Al1 of the above

You are managing a project that will implement a new Insurance software package. Two project team members have difficulty working together. They come to you, for help resolving the issues. You immediately set up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. What type of organizational structure you are working in?

A.

Functional

B.

Balanced matrix

C.

Piojectized

D.

Strong Matrix

Lessons learned session should be held at what point in a project?

A.

At the project conclusion

B.

At key milestones

C.

When risk events occur

D.

When sponsor want

Which of the following activity is not performed as part of the direct and manage project execution process?

A.

Monitor implementation of approved changes

B.

Validate deliverables

C.

Staff, train, and manage the project team

D.

Manage cisks and implement risk responses

ISO Stands for __________.

A.

International Organization for Standardization

B.

International Standardized Organization

C.

'n Standardized Organization

D.

Indiana Standardized Organization

What is a corrective action?

A.

An action that brings future project events Into alignment with the project plan

B.

An action to correct something in the project

C.

An action to prevent something in the project

D.

Corrective action is not related to project

If a project with a CPI of 1.6, what you tell?

A.

The project is consuming fewer resources than anticipated

B.

The project is using fewer resources than anticipated.

C.

The project is falling behind.

D.

The project is running ahead of schedule.

Which of the following are the inputs of Define Scope?

A.

Requirements document created in collect requirements process

B.

Project files from previous projects

C.

Project Charter

D.

Al1 of the above

The end of the project comes after which of the following?

A.

Project charter

B.

F'na' deliverable

C.

Schedule

D.

QA activities are done

When you are developing the estimates for project, you choose to add the individual estimates for the activities that comprise each phase. What type of estimation method are you using?

A.

Parametric estimating

B.

Bottom-up estimating

C.

Top-down estimating

D.

Analogous estimating

You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?

A.

Schedule

B.

Assumption

C.

Constraint

D.

Planning process

Assumptions are factors that, for planning purposes, are considered to be ______.

A.

True, real, or certain

B.

True, real, or uncertain

C.

Real

D.

Verbal