When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

A.

event.

B.

response,

C.

perception.

D.

impact.

A tool or technique used during the Administer Procurements process is:

A.

Expert judgment.

B.

Bidder conference.

C.

Procurement negotiation.

D.

Performance reporting.

Which type of control tool identifies whether or not a process has a predictable performance?

A.

Cause and effect diagram

B.

Control Charts

C.

Pareto Chart

D.

Histogram

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

A.

ends.

B.

begins.

C.

delays.

D.

deviates.

Which process occurs within the Monitoring and Controlling Process Group?

A.

Control Costs

B.

Plan Quality

C.

Perform Quantitative Risk Analysis

D.

Determine Budget

An input to the Control Quality process is:

A.

Activity attributes

B.

Quality control measurements

C.

Enterprise environmental factors

D.

Deliverables

Testing falls into which of the following categories of cost of quality?

A.

Internal failure costs

B.

Prevention costs

C.

Appraisal costs

D.

External failure costs

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

A.

Project Communications Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Scope Management

An input to the Plan Procurement Management process is:

A.

Source selection criteria.

B.

Market research.

C.

A stakeholder register.

D.

A records management system.

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

A.

Perform Quality Control

B.

Quality Metrics

C.

Perform Quality Assurance

D.

Plan Quality

What is the term assigned to products or services having the same functional use but different technical characteristics?

A.

Scope

B.

Quality

C.

Specification

D.

Grade

The process to ensure that appropriate quality standards and operational definitions are used is:

A.

Plan Quality.

B.

Perform Quality Assurance.

C.

Perform Quality Control.

D.

Total Quality Management.

What is the critical chain method?

A.

A technique to calculate the theoretical early start and finish dates and late start and finish dates

B.

A schedule network analysis technique that modifies the project schedule to account for limited resources

C.

A schedule compression technique that analyzes cost and schedule trade-offs to determine how to obtain the greatest amount of compression for the least incremental cost

D.

A technique to estimate project duration when there is a limited amount of detailed information about the project

Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

A.

Bottom-up

B.

Three-point

C.

Parametric

D.

Analogous

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

A.

Human resource management plan.

B.

Activity resource requirements.

C.

Personnel assessment tools,

D.

Multi-criteria decision analysis.

Change requests are an output from which Project Integration Management process?

A.

Direct and Manage Project Execution

B.

Develop Project Management Plan

C.

Close Project

D.

Develop Project Charter

What is the primary benefit of meeting quality requirements?

A.

Quality metrics

B.

Less rework

C.

Quality control measurements

D.

Benchmarking

An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:

A.

smooth/accommodate.

B.

force/direct,

C.

collaborate/problem solve,

D.

compromise/reconcile.

Which of the Project Time Management processes analyzes activity sequencing, durations, resource requirements, and schedule constraints?

A.

Estimate Activity Durations

B.

ControlSchedule

C.

Sequence Activities

D.

Develop Schedule

Which knowledge area employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

A.

Project Risk Management

B.

Project Integration Management

C.

Project Communications Management

D.

Project Quality Management