Which schedule format usually shows both the project network logic and the project's critical path schedule activities with activity date information?

A.

Schedule table

B.

Schedule network diagram

C.

Bar chart

D.

Milestone chart

Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work-days. What should be your concern?

A.

There is a cost under run.

B.

There is a cost overrun.

C.

May not meet deadline.

D.

The project is 20 days behind schedule.

What is the name of a graphic display of project team members and their reporting relationships?

A.

Role dependencies chart

B.

Reporting flow diagram

C.

Project organization chart

D.

Project team structure diagram

Which is a tool or technique used in scope definition?

A.

Templates, forms and standards

B.

Change requests

C.

Stakeholder analysis

D.

Project assumptions

What does a CPI value greater than 1.0 indicate?

A.

Cost right at the estimated value

B.

Cost under the estimated value

C.

Cost right at the actual value

D.

Cost over the estimated value

A weighting system is a tool for which area of procurement?

A.

Plan contracting

B.

Request seller responses

C.

Select sellers

D.

Plan purchase and acquisition

What characteristic do project and operational work share in common?

A.

Performed by systems

B.

Constrained by limited resources

C.

Repetitiveness

D.

Uniqueness

How is scheduled variance calculated using the earned value technique?

A.

EV less AC

B.

AC less PV

C.

EV less PV

D.

AC less EV

An input required to develop a preliminary project scope statement is:

A.

Organizational Structure

B.

Organizational Process Assets

C.

Organizational Matrix

D.

Organizational Breakdown Structures

Which of the following is an input to Develop Human Resource Plan?

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

Who selects the appropriate processes for a project?

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Which enterprise environmental factors are considered during cost estimating?

A.

Marketplace conditions and commercial databases

B.

Marketplace conditions and company structure

C.

Commercial databases and company structure

D.

Existing human resources and market place conditions

Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

A.

The influence of the stakeholders increases, the cost of changes increases.

B.

The influence of the stakeholders decreases, the cost of changes increases.

C.

The influence of the stakeholders increases, the cost of changes decreases.

D.

The influence of the stakeholders decreases, the cost of changes decreases.

Which type of analysis is used to develop the communications management plan?

A.

Product

B.

Cost benefit

C.

Stakeholder

D.

Research

Which type of analysis is used as a general management technique within the Plan Procurements Process?

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis