An InfiniBand server stops working, and a system administrator runs the " ibstat " command that provides the following output:

CA ' mlx5_1 '

CA type: MT4115

Number of ports: 2

Firmware version: 10.20.1010

Hardware version: 0

Node GUID: 0x0002c90300002f78

System image GUID: 0x0002c90300002f7b

Port 1:

State: Initializing

Physical state: Linkup

Rate: 100

Base lid: 0

LMC: 0

SM lid: 0

Capability mask: 0x0251086a

Port GUID: 0x0002c90300002f79

Link layer: InfiniBand

What is the cause of the issue?

A.

The HCA port is faulty.

B.

There is no running SM in the fabric.

C.

The neighboring switch port is faulty.

D.

The cable is disconnected.

You are standing up an NVIDIA DGX system for enterprise production. Stakeholder teams require system reliability, performance consistency under load, and proper escalation processes before release. A recent system in another cluster experienced intermittent GPU failures attributed to missed early-stage validation. Which deployment and validation sequence best addresses production readiness and mitigates the risk of avoidable downtime or performance loss?

A.

Install latest OS images and drivers, confirm OS and container functionality, invite users for a monitored production trial, and collect workload feedback to plan any further diagnostics or updates.

B.

Complete hardware and cabling, power on the system, update firmware and drivers, run full hardware health checks and stress diagnostics using NVSM, verify all GPU and system sensor logs, and validate GPU accessibility.

C.

Update network topology, assign static IPs and DNS entries, register the system with NVIDIA, then conduct basic OS-level checks and enable user access after login testing is successful.

D.

Power on the system, install all AI frameworks, configure the CUDA and library stack, set up user environments, then plan stress tests and diagnostics as part of ongoing routine operations.

You are evaluating the integration of NVIDIA BlueField DPUs into your data center ' s storage architecture to optimize AI workloads. The storage solution chosen has incorporated BlueField DPUs to enhance performance and efficiency. Which of the following benefits directly results from this integration?

A.

Unlimited scalability by adding more DPUs without architectural changes.

B.

Elimination of latency issues in data processing tasks.

C.

Reduced CPU load by offloading data processing tasks to DPUs.

D.

Enhanced I/O performance with NVMe storage access speeds.

An engineer needs to verify the current firmware versions of all components (ATF, BSP, NIC, UEFI) on a BlueField-3 DPU ' s BMC. Which Redfish API command provides this information?

A.

mlxconfig -d < dev > q

B.

curl -k -u root: < password > -X GET https:// < DPU-BMC-IP > /redfish/v1/UpdateService/FirmwareList

C.

mstflint -d < PCI_ID > query full

D.

curl -k -u root: < password > -X GET https:// < DPU-BMC-IP > /redfish/v1/UpdateService/FirmwareInventory

As the infrastructure lead for an NVIDIA AI Factory deployment, you have just uploaded the latest supported firmware packages to your DGX system. It is now critical to ensure all hardware components run the new firmware and the DGX returns to full operational capability. Which sequence best guarantees that all relevant components are correctly running updated firmware?

A.

Perform a software-driven restart on the operating system of every compute node, then use advanced tools to check firmware status, and reissue update commands if any firmware appears inactive afterward.

B.

Execute a single AC power cycle on the DGX after the update process, then reset the software stack and verify status using diagnostic commands on each node for confirmation of all component updates.

C.

Initiate a cold power cycle on all node trays to activate firmware, follow with a DGX reboot procedure, and use the management interface to finish activating CPLD firmware on the host.

D.

Initiate a cold power cycle on the system to activate firmware for components, reset the BMC using the recommended command, and perform an AC power cycle to ensure EROT and CPLD firmware is activated.

A system administrator needs to configure a BlueField DPU and enable RShim on the baseboard management controller (BMC). Which command should be executed?

A.

ipmitool raw 0x32 0x6a 1

B.

systemctl restart rshim

C.

systemctl enable bmc-rshim.service

D.

scp < path_to_bfb > root@ < bmc_ip > :/dev/rshim0/boot

You are installing the operating system as part of the initial setup for a new NVIDIA Base Command Manager (BCM) cluster. Which two of the following actions are essential for a successful OS installation on the cluster ' s head node? (Pick the 2 correct responses below)

A.

Configure network switches for PXE boot to all compute nodes before installing the OS on the head node.

B.

Download the latest BCM ISO and verify its integrity using the provided checksum, then start the installation.

C.

Start the head node OS installation process with the system BIOS set to legacy boot mode instead of UEFI.

D.

Set the desired time zone and configure NTP synchronization during the OS installation wizard.

ClusterKit ' s NCCL bandwidth test shows 350 GB/s on a 400G InfiniBand fabric. How should this result be interpreted?

A.

Optimal performance, indicating healthy fabric and GPUDirect RDMA.

B.

Suboptimal performance; requires FEC tuning to reach 380+ GB/s.

C.

Critical failure; expected is > 390 GB/s for HDR InfiniBand.

D.

Inconclusive; rerun with --stress=cpu to validate.

A system administrator needs to validate a GPU-based server and ensure that no errors occur under load. What command should be used?

A.

nvsm dump health

B.

stress-test --usage

C.

nvsm show health

D.

nvsm stress-test

What is the primary purpose of performing a NeMo burn-in on a new AI infrastructure?

A.

To benchmark production training speed and ensure all GPUs are running at identical clock speeds.

B.

To stress test the hardware and software stack with representative NeMo workloads, ensuring reliability.

C.

To tune NeMo model hyperparameters for maximum accuracy on user datasets during cluster deployment.