Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exc65

An architect's client is focused on lighting energy savings and daylighting design in a new 3,000 ft² commercial building addition to expand showroom and office square footage. The client requests reasonable daylighting measures in the design.

What should the architect recommend to the client?

A.

Isolate electric lighting for daylight-responsive control to within a single zone

B.

Provide for daylight-responsive control of electric lighting

C.

Limit ample access to daylight to the interior spaces only

D.

Increase sunlight in the vicinity of critical visual tasks

An elementary school requires a renovation, selective demolition, and a major addition in order to accommodate a growing student population. The school is located in a temperate coastal climate that requires almost equal heating and cooling days during the year. Good indoor air quality and increased energy efficiency are priorities.

Given the building use and site location, which of the following approaches should be used for the mechanical system in the school?

A.

Hydronic Convection System

B.

Geothermal System

C.

Single Duct Constant Air Volume (CAV)

D.

Evaporative Cooling and Trombe Wall

An architect is designing a multistory student housing project to be built of light wood framing. The following criteria must be met:

Minimize the floor assembly thickness

Maximize ceiling height

No individual HVAC room controls

No exposed ductwork

Which HVAC system should be selected for this project?

A.

Packaged terminal units (PTAC)

B.

Four-pipe fan-coil system

C.

Variable air volume (VAV)

Refer to the exhibit (stair connecting four stories, occupant load 100, not accessible exit).

Not including the permitted projection for handrails and stringers, what is the minimum clear width of the stair at dimension X?

A.

36 inches

B.

44 inches

C.

48 inches

D.

60 inches

Heavy steel columns and rigid connections between columns and beams

Vertical steel trusses in the external walls

Light steel columns and flexible connections between columns and beams

Vertical steel trusses in the internal walls

Which structural design concept minimizes the cost of steel structure needed to resist wind and earthquake loads in high-rise buildings?

A.

Heavy steel columns and rigid connections between columns and beams

B.

Vertical steel trusses in the external walls

C.

Light steel columns and flexible connections between columns and beams

D.

Vertical steel trusses in the internal walls

The architect's greatest contribution to good seismic design is in the design of which of the following?

A.

Structural components and connections

B.

Building's interior partition arrangement

C.

Building's plan and cross-sectional configuration

D.

Site location and building orientation

A one-story residence in a dry climate with cold winter nights is designed with an unconditioned dirt floor crawlspace utilizing underfloor plumbing and HVAC ductwork. The owner is interested in using a concrete slab-on-grade floor instead of the pier-and-beam concrete floor over an open crawlspace as originally designed.

What are the impacts of changing the design to a slab-on-grade floor system? Check the two that apply.

A.

It will have warmer floors in the evenings.

B.

It will have more steel reinforcing.

C.

It will limit future plumbing flexibility.

D.

It will limit the types of flooring finishes available.

E.

It will allow for better moisture control.

F.

It will allow for HVAC ductwork installation.

Refer to the exhibit (concrete rigid frame building with aluminum curtain wall system).

The drawing shows a proposed concrete rigid frame building enclosed in an aluminum curtain wall system. To save money, the contractor proposed to eliminate the curtain wall system and substitute steel stud framing, which is anchored between the columns and beams and covered with a stucco finish.

What is the most likely result of this substitution?

A.

Wind load on the stud framing will transfer directly to the concrete frame and overload it.

B.

The substitution will work and will save construction cost.

C.

The stucco will crack due to movement of the frames under lateral loading.

D.

Increased dead load of the stucco system will overload the frames.

A new gallery is being built and requires shading elements to protect the light-sensitive artwork on display.

Which of the following are design criteria relevant to the design of shading components on the west facade of the new gallery? Check the three that apply.

A.

Height of the west gallery wall

B.

Annual temperature data

C.

Solar Heat Gain Coefficient of the west glazing

D.

Spacing and depth of vertical louvers

E.

Low-E glazing on the west facade

F.

Survey of adjacent building heights

An elementary school requires a renovation, selective demolition, and a major addition in order to accommodate a growing student population. An architectural firm has prepared schematic design plans incorporating the school's increased programmatic needs, including an enlarged library, cafeteria, and gymnasium; a secure courtyard; and additional space for administrative offices and classrooms. The main entrance was relocated in order to improve the traffic and pedestrian flow at the beginning and end of the school day, and additional parking was provided to comply with current zoning requirements.

The existing single-story masonry building was built in 1950. Two small additions were built later: the north addition will be kept and repurposed, but the south addition will be demolished. The building contains asbestos and lead in roof soffits, floor tiles, pipe insulation, and window paint. All existing mechanical systems need to be replaced; new systems have not been selected.

Considerations for the renovation include:

    The relocated front entrance must be easily recognizable, highly visible, and secure.

    Interior and exterior materials need to be durable and maintainable in order to withstand frequent student abuse, but also economical due to strict budget limitations.

    Good indoor air quality and increased energy efficiency are priorities for the selection of mechanical equipment.

After completion, the entire school should look uniform, without a distinctive difference between the existing building and new addition.

Building information:

    Construction Type is II-B.

The following resources are available for your reference:

    Existing Plans, including site and floor plans

    Proposed Plans, including site and floor plans

    Cost Analysis

    Zoning Ordinance Excerpts, for off-street parking requirements

    IBC Excerpts, showing relevant code sections

    ADA Standards Excerpts, showing relevant sections from the ADA Standards for Accessible Design

Which of the following is the maximum height the platform can be above the gymnasium floor per the proposed design?

A.

2'-6"

B.

1'-9"

C.

1'-6"