Iteration planning for Sprint 5 of your current project is complete. The plan for the sprint is to increase performance of the system, which of the following acceptance criteria would you expect for Sprint 5?

i) User access for all roles has been validated.

ii) A static analysis tool has been executed for all code.

iii) 100% of the existing regression test suite has passed.

Iv) System is responding In less than 3 seconds, 90% of the time.

v) A new version of Internet Explorer has been included.

SELECT ONE OPTION

A.

ii, v

B.

iii, iv

C.

iv, v

D.

i, iii

Which of the following describes the main purpose of a task management tool in agile projects?

SELECT ONE OPTION

A.

A task management tool allows developers to continuously integrate their code.

B.

A task management tool is used by team members to share ideas and collaborate on assigned tasks.

C.

A task management tool is used to manage and track user stories, tests and other tasks.

D.

A task management tool is used to store source code and automated tests.