Which of the following are the characteristics of the project life cycle?

Each correct answer represents a complete solution. Choose all that apply.

A.

Cost and staffing are low at the start, are high as the work is carried out, and decrease as the project comes towards the end.

B.

Stakeholders influences, risk, and uncertainty are at peak in the beginning of the project.

C.

Skills to influence the final characteristics of the project's product, without much impact on cost, is at peak in the beginning of the project and reduces as the project progresses towards completion.

D.

It is limited by constraints, including resource constraints.

You work as a project manager for PassGuide Inc. You are working on the Plan quality process for your project. Which of the following are inputs of the Plan quality process?

Each correct answer represents a complete solution. Choose all that apply.

A.

Scope baseline

B.

Stakeholder register

C.

Project document updates

D.

Cost performance baseline

You work as a project manager for PassGuide Inc. You are working on directing and managing the execution of your project. Which of the following is the most likely outcome as part of this phase of the project?

A.

Quality control measurements

B.

Quality metrics

C.

Deliverables

D.

Organizational process assets update

Which of the following documents is described in the statement below?

"It is an exchange of promises between two or more parties to do an act which is enforceable in the court of law."

A.

Risk register

B.

Contract

C.

Project calendar

D.

Resource calendar

Which of the following are the characteristics of a project?

Each correct answer represents a complete solution. Choose all that apply.

A.

Its success is measured by evaluating whether it meets or exceeds expectations of the stakeholders.

B.

It is temporary in nature and has a definite beginning and ending date.

C.

It is completed when the project goals are achieved.

D.

It is common in nature.

Fill in the blank with the appropriate term.

The______ defines the period in which, during the development of the project scope statement, a clear and very thorough project scope statement narrative is documented.

The Project Communications Management knowledge area focuses on which of the following processes?

Each correct answer represents a complete solution. Choose all that apply.

A.

Identify Stakeholders

B.

Distribute Information

C.

Create Work Breakdown Structure (WBS)

D.

Report Performance

You are the project manager for the HGQ Project. You and the project team are currently working on the Identify Risks process. When does this project typically happen in a project?

A.

During project execution

B.

During project initiation

C.

Throughout the entire project

D.

During project monitoring and controlling

Which of the following are inputs of the perform quality assurance process?

Each correct answer represents a complete solution. Choose all that apply.

A.

Change requests

B.

Quality metrics

C.

Work performance information

D.

Project management plan

Which of the following processes is described in the statement below?

"It is the process of identifying the specific actions to be performed to produce the project deliverables."

A.

Define Activities

B.

Define Scope

C.

Sequence Activities

D.

Create WBS