Which of the following processes is described in the statement below?

"It is the process of identifying the specific actions to be performed to produce the project deliverables."

A.

Define Activities

B.

Create WBS

C.

Define Scope

D.

Sequence Activities

Alan works as a project manager for PassGuide Inc. He is working on the office renovation project. The office has 200 doors. All doors have to be glassed and painted. Before each door can be painted, the glasses must be fitted in them at least 12 hours before. Alan has arranged these tasks with a finish to start relationship between glassing and painting. What else should Alan do to account for the twelve hours of maintenance time?

A.

Alan must add twelve hours of lead time to each of the 200 doors painting activity to account for the glassed maintenance time.

B.

Alan must schedule all 200 office doors to be glassed first and then schedule all 200 doors to be painted to ensure time for the maintenance.

C.

Alan must add twelve hours of lag time to each of the 200 doors painting activity to account for the glassed maintenance time.

D.

Alan must add an intermediary task with duration of twelve hours.

You are the project manager for your organization. Your organization manages projects for other companies. You will be soon managing a project for the JUH Company. What document do you need first to help to develop the project charter?

A.

Business requirements

B.

Functional requirements

C.

Preliminary project scope statement

D.

Contract

Which of the following are outputs of the Perform Integrated Change control process?

Each correct answer represents a complete solution. Choose all that apply.

A.

Work performance information

B.

Project management plan update

C.

Project document update

D.

Change request status update

Which of the following are inputs of the Develop project team process?

Each correct answer represents a complete solution. Choose all that apply.

A.

Project management plan

B.

Team performance assessment

C.

Project staff assignment

D.

Resource calendar

Identify Risks is the process of determining which risks may affect the project. Which of the following are inputs of the Identify risks process?

Each correct answer represents a complete solution. Choose all that apply.

A.

Risk register

B.

Scope baseline

C.

Project documents

D.

Risk management plan

You work as a project manager for PassGuide Inc. You are working on the control schedule process. Which of the following techniques will you use to find ways to bring project activities that are behind into alignment with the plan?

A.

Resource leveling

B.

What-if scenario analysis

C.

Adjusting leads and lags

D.

Schedule compression

You work as a project manager for PassGuide Inc. Which of the following processes will you use to build up an estimate of the monetary resources required to complete project activities?

A.

Determine budget

B.

Control costs

C.

Estimate costs

D.

Plan quality

In which of the following forecasting techniques is an attempt made to develop forecasts through group consensus?

A.

Time series method

B.

Casual/econometric method

C.

Delphi technique

D.

Judgmental forecasting method

Which of the following contract types is described in the statement below?

"This contract type provides no incentive for the contractor to control costs and hence is rarely utilized."

A.

Cost Plus Fixed Fee

B.

Cost Plus Award Fee

C.

Cost Plus Percentage of Cost

D.

Cost Plus Incentive Fee