Black Friday Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

Which of the following processes formally permits the initiation of a project and marks the kickoff for all consequent development activities to begin?

A.

Develop project charter

B.

Develop project management plan

C.

Develop project scope statement

D.

Develop project team

James works as the project manager for a software project. He and his team are on the Direct and Manage Project Execution process. All of the following are inputs of this process except for which one?

A.

Project charter

B.

Approved environmental requests

C.

Organizational process assets

D.

Enterprise environmental factors

E.

Project management plan

You are in need of procuring several tons of pea gravel for a construction. You'll need the vendor to provide a bid for the pea gravel on a specific date and time and that's one of the requirements included in the procurement document package you are reviewing. Who creates the procurement document package?

A.

The project sponsor

B.

Both parties contribute

C.

The seller

D.

The buyer

Which of the following is described in the statement below?

"It is a tool that defines a project and groups the project's discrete work elements in a way that helps organize and define the total work scope of the project."

A.

WBS

B.

RBS

C.

Gantt chart

D.

Critical path

Which of the following documents is described in the statement below?

"It is a companion document to the WBS. It describes each component in the WBS. It includes a brief definition of the scope or statement of work, defined deliverables, a list of associated activities, and a list of milestones. It details all work packages in WBS including estimates and billing information."

A.

WBS dictionary

B.

Contract

C.

Project charter

D.

Activity list

You work as a project manager for PassGuide Inc. You report the project details directly to the vice president and the administrator of your organization. In which of the following types of organization structures are you working?

A.

Functional

B.

Matrix

C.

Jury

D.

Projectized

Which of the following types of organizational structures represents a hierarchy where every member has one leader and the employees are grouped by the area of expertise?

A.

Matrix

B.

Functional

C.

Jury

D.

Projectized

Which of the following is described in the statement below?

"It contains a complete set of indexed contract documentation. It is prepared to be included with the final project files."

A.

Procurement file

B.

Project charter

C.

Stakeholder register

D.

Risk register

You work as a project manager for PassGuide Inc. You have to subdivide project deliverables and project work into smaller, more manageable components. Which of the following processes will you use to perform the above task?

A.

Create WBS

B.

Verify scope

C.

Control scope

D.

Define activities

You work as a project manager for PassGuide Inc. You are performing a task to generate a hierarchical list of resources related by function and resource type that is used to facilitate planning and controlling of project work. Which of the following components of project management will you use to accomplish the above task?

A.

PERT chart

B.

RBS

C.

Gantt chart

D.

WBS