You are the Contract Manager of the Employer for a Data Centre Project using the FIDIC Yellow Book (edition 2017). As a Contract Manager during the procurement stage, you are to explain the difference between Dispute Avoidance and Adjudication Board (DAAB) and other alternative dispute resolutions for this type of project. Which one of the following statements of its explanation is NOT correct?
Under the FIDIC Silver Contract (edition 2017), which two of the answers provide for preconditions for certification and payment of the Interim Payment Certificate?
Choose all of the correct answers (multiple possibilities).
(During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers discovers a possible ancient treasure on the Site. The supervisor stops the Works, secures the Site, and informs the Engineer. How should the Engineer react?)
For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor ' s reporting requirement end?
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?
Under the FIDIC Yellow Book (both editions), the Contract is administered by the Employer (unless it appoints an Employer ' s Representative) who endeavours to reach agreement with the Contractor on each claim. Is this statement true or false?
Which two statements are true under the FIDIC Red Book (edition 1999)?
(Choose all of the correct answers — multiple possibilities)
Which of the following situations form legally binding contracts? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities)
If the Engineer is required to obtain the Employer ' s prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
(You are the Contract Manager of the Employer ' s Representative in a Thermal Power Plant Project under FIDIC Silver Book (edition 2017). The Contractor submits two claims:
(1) USD 200,000 for additional costs due to an error in national piling standard NTS-PW-01 referenced in the Employer’s Requirements.
(2) USD 300,000 for constructing an additional flood wall due to incorrect hydrological data in Site Data (water level miscalculated).
What is your determination for the Contractor?)