Spring Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

You are the Contract Manager of the Employer for a Data Centre Project using the FIDIC Yellow Book (edition 2017). As a Contract Manager during the procurement stage, you are to explain the difference between Dispute Avoidance and Adjudication Board (DAAB) and other alternative dispute resolutions for this type of project. Which one of the following statements of its explanation is NOT correct?

A.

DAAB is to provide for a fair, timely and efficient resolution of Disputes.

B.

The function of the DAAB is to remain in place as part of the Parties ' project team to assist both Parties, equally and impartially.

C.

Avoidance of Disputes on the project and resolution of Disputes at or soon after the time they arise is a two-part role of the DAAB.

D.

DAAB provided supports for Parties during arbitration, as a witness to give factual evidence on the background for the DAAB ' s Decision.

Under the FIDIC Silver Contract (edition 2017), which two of the answers provide for preconditions for certification and payment of the Interim Payment Certificate?

Choose all of the correct answers (multiple possibilities).

A.

The appointment of the Contractor and receipt of the Advance Payment Guarantee, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 14.2.1.

B.

Receipt of a statement via a letter showing the amounts to which the Contractor considers itself to be entitled.

C.

The appointment of the Contractor ' s Representative and receipt of the Performance Security, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 4.2.1.

D.

Receipt of a statement and supporting documents.

(During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers discovers a possible ancient treasure on the Site. The supervisor stops the Works, secures the Site, and informs the Engineer. How should the Engineer react?)

A.

You compliment the supervisor and ask him to excavate further and personally deliver the treasure to a university. No extension of time is granted.

B.

You thank the supervisor, secure the Site, instruct guarding measures, inform the Employer and authorities, and issue a Variation to cover the costs of protection measures.

C.

You inform the supervisor that a formal written notice under Sub-Clause 4.24 is required and no further instruction can be given until then.

D.

You instruct the supervisor to cover the finding and resume the Works immediately, and make a determination later.

For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor ' s reporting requirement end?

A.

After issuance of the Taking-Over Certificate.

B.

After issuance of the Performance Certificate.

C.

At the Date of Completion of the Works (irrespective of whether there is minor outstanding work to be performed).

D.

Until all outstanding works as stated in the Taking-Over Certificate are completed.

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?

A.

True

B.

False

Under the FIDIC Yellow Book (both editions), the Contract is administered by the Employer (unless it appoints an Employer ' s Representative) who endeavours to reach agreement with the Contractor on each claim. Is this statement true or false?

A.

True

B.

False

Which two statements are true under the FIDIC Red Book (edition 1999)?

(Choose all of the correct answers — multiple possibilities)

A.

The Performance Certificate is deemed to constitute the acceptance of the Works.

B.

The Performance Certificate constitutes acceptance of the Works and full performance of all obligations of each Party.

C.

The Engineer shall issue the Performance Certificate within 28 days at the latest: by the end of the Defects Notification Periods, and once the Contractor has supplied all the Contractor ' s Documents and completed and tested all Works including remedying any defects in accordance with the Contract.

D.

The Performance Certificate is deemed to be issued on fulfilment of certain conditions stated in the respective Sub-Clause.

Which of the following situations form legally binding contracts? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities)

A.

The Employer received the Contractor ' s Letter of Tender and issued a Letter of Intent.

B.

The Employer and the Contractor signed the Contract Agreement.

C.

The Employer received the Contractor ' s Letter of Tender and issued a conditional Letter of Acceptance.

D.

The Employer received the Contractor ' s Letter of Tender and issued Letter of Acceptance.

If the Engineer is required to obtain the Employer ' s prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

A.

Remain silent and not do anything in the subject.

B.

The Engineer should refer the matter in subject to the DAB.

C.

Issuing the determination to the Contractor in the form and with the content agreeable to the Employer, with a remark, that it is the Employer ' s determination and not the Engineer ' s determination.

D.

Informing the Contractor of their inability of issuing the determination, in lack of the Employer ' s necessary approval.

(You are the Contract Manager of the Employer ' s Representative in a Thermal Power Plant Project under FIDIC Silver Book (edition 2017). The Contractor submits two claims:

(1) USD 200,000 for additional costs due to an error in national piling standard NTS-PW-01 referenced in the Employer’s Requirements.

(2) USD 300,000 for constructing an additional flood wall due to incorrect hydrological data in Site Data (water level miscalculated).

What is your determination for the Contractor?)

A.

The Contractor is not entitled to either of the Claims.

B.

The Contractor is entitled to the Claim for additional costs in relation to the piling, based on errors in the Employer ' s Requirements only.

C.

The Contractor is entitled to the Claim for the additional floodwall based on Unforeseeable difficulties only.

D.

The Contractor is entitled to both claims.