What is unlikely to be included in the outline business case for NEWGEN?
ZYXS has been appointed as the service integrator The CIO of ZYX would like to disband the IT Steering Group. She wants the former Product Development Forum to be expected to include representatives from every provider.
This new body will be known as the Services Steering Group (SSG). The responsibilities of the SSG will include approving the design and funding for new products and services and the supporting architectures, setting policies for related governance, and considering new technologies that can assist with achieving the goals of the ZYX corporate strategy. The SSG will be chaired by the ZYXS IT Director.
The representatives of the SSG must be empowered to take decisions on behalf of their organizations
What type of structural element is this steering group*?
ZYX has appointed SIAMRUS and the service management staff from ZYXS as a hybrid service integrator They will use the SIAM model from SIAMRUS
The IT staff from ZYXS and ZYXUK will form a new internal service provider. ZYXSAPP. ZYXSAPP will provide the services for application development and application support
ZYXH will provide the retained capabilities The contract with OUTSCO will not bo renewed ZYX wants to start planning the implementation of the SIAM model
What should SIAMRUS do that would most support ZYX?
ZYXS has been selected as the service integrator. The ZYXS Service Management and Service Desk Lead is the process owner of the change management process. Service providers are allowed to develop their own procedures. The IT Director has asked for a metric for the change management process that aligns with the SIAM principles of measurement
Which is the best metric?
The planning for NEWGEN has started
-ZYXS will be the service integrator
-OUTSCO will provide application support services
-NETSCO will provide network services.
-PAYSCO is asked to continue to provide payroll services
Users are happy with the services of PAYSCO The contract with PAYSCO has 2 years left to run This is 18 months after the expected completion date ot the implementation of the SIAM model Initial discussions by ZYXS with PAYSCO have indicated that PAYSCO does not want to make any contract changes to support the SIAM model.
Given this constraint what is most likely to be the best method to plan for onboarding PAYSCO?
Project NEWGEN is in the Discovery and Strategy stage. SIAMRUS is assisting ZYX with the design of the SIAM model ZYX has decided to use OUTSCO as an external service integrator but they have not yet been appointed.
The CIO is concerned that the retained capabilities might not have the necessary capability to perform their new role in the SIAM model
What is the best course of action?