A data center has its own power supply from the public utility and receives chilled water supply from the building owner.

What needs to be taken into consideration when calculating the PUE?

A.

Nothing, as the chiller plant in the building also uses electrical power

B.

You will need to take the value for COP of the chiller plant into consideration

C.

You will need to take a weight factor of 0.4 for district chilled water into consideration

D.

PUE calculations are not possible in shared buildings

The data center has been in operation for about 1 year and 2 months. The dust levels in the computer room are relatively high.

What is the most likely root cause?

A.

The cleaning crew is not doing their work properly

B.

Every computer room has high dust levels due to constant high-speed air movement

C.

Low pressure in the computer room

D.

Floorboards are most likely not fitted correctly

What is the advantage or disadvantage of using MPO (Multi-fiber Push On)/pre-terminated fiber?

A.

There is no advantage, as it cannot be used with OM4 optical fiber cables.

B.

There is no advantage, as it creates additional heat load in the data center.

C.

It speeds up installation and provides an easy upgrade to transmission speeds up to 40 Gbit/s -100 Gbit/s.

D.

It is a very flexible system as it can be used for both copper cables and optical fiber cables.

What is the minimum requirement for the power feeds to the building for a Rated-3 data center based on the ANSI/TIA-942 standard?

A.

Two feeds coming from two different substations, one power company is not acceptable

B.

Two feeds coming from two different substations, one power company is acceptable

C.

Two feeds entering the data center building from one substation

D.

One feed from one substation split over two separated distribution boards in separate rooms

In order to save energy, you are going to install an automated system to switch off lights. What should be taken into consideration when installing such a system?

A.

Security guards should perform regular inspections verifying the system works.

B.

The system should not be based on motion detection as the lights might suddenly switch off while staff is still at work.

C.

It is not advisable to use such a system since it will reduce the lifetime of LED lighting.

D.

At all times, the levels should allow for security cameras to function properly.

What is the main disadvantage of using a ToR (Top of Rack) design?

A.

A single ToR (Top of Rack) switch is more expensive than an EoR (End of Row) switch.

B.

You need a separate rack to install all your ToR (Top of Rack) switches.

C.

There will be more switches to manage.

D.

A ToR (Top of Rack) switch has only optical interfaces.

A data center scores Rated-3 in mechanical, Rated-4 in electrical, and Rated-2 in architectural.

What is the overall Rating of this data center when the Rating is based on the ANSI/TIA-942?

A.

Rated-2 since that is the lowest rating received

B.

Rated-4 since that is the highest rating received

C.

Rated-4 since electrical is more important than mechanical and architectural

D.

Depends on the Rating scored in telecommunications

A computer room with a raised floor has been designed with racks in a hot/cold aisle setup.

What should you recommend for the placement of down-flow air conditioners?

A.

Air conditioners perpendicular to (at the end of the row of) the Cold-Aisle

B.

Air conditioners perpendicular to (at the end of the row of) the Hot-Aisle

C.

Air conditioners should always be placed at both sides of each row of racks

D.

Air conditioner placement has no influence on cooling effectiveness and efficiency. Hence, they can be placed at any convenient location.