During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13.

What is the velocity of the team?

A.

18

B.

24.5

C.

31

What is a Sprint?

A.

A brainstorming session in Extreme programming to generate design ideas.

B.

A race between two developers to see who can complete a feature fastest.

C.

One iteration in the Scrum methodology.

D.

The last iteration in the Scrum project, when the team works long hours to finish the project.

A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.

What is the elapsed time required to complete the story?

A.

1.25 days

B.

1.33 days

C.

2 days

D.

This cannot be determined without knowing the velocity.

From which sport is the term "Scrum" and much of the terminology derived?

A.

Kick boxing

B.

Polo

C.

Rugby

D.

Soccer

Which statement describes Release Planning?

A.

After looking at all the stories in the backlog, the team estimates their effort in detail.

B.

The team meets with the customer to negotiate the scope, cost and time of the release.

C.

The team and the Product Owner agree on an initial plan for the delivery of features.

Which is a statement of value as described in the Agile manifesto?

A.

We value customer collaboration over responding to changes.

B.

We value project management over individuals and interactions.

C.

We value processes and tools over comprehensive documentation.

D.

We value responding to change to satisfy the customer.

What is meant by the velocity of the team?

A.

The rate a team puts in a normal work day.

B.

The rate at which features are released to the customer.

C.

The rate at which the team completes the work.

D.

The rate at which the team renews itself.