During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13.
What is the velocity of the team?
What is a Sprint?
A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.
What is the elapsed time required to complete the story?
From which sport is the term "Scrum" and much of the terminology derived?
Which statement describes Release Planning?
Which is a statement of value as described in the Agile manifesto?
What is meant by the velocity of the team?