Black Friday Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

The general principle to which architects and engineers have a duty to clients and society at large to practice is defined as "taking the same course of action as another reasonable and prudent architect or engineer in the same geographic area would have taken under the same circumstances" is known by what term?

A.

Professional standard of care

B.

Due diligence

C.

Performance based requirement

D.

Spearin doctrine

Who is responsible for accepting and inspecting for damage of the owner-furnished products delivered to the project site?

A.

Contractor

B.

Installer

C.

Owner

D.

Subcontractor

The names of the project, owner, architect/engineer and consultants, and the general project data such as a location map are normally included in which of the following?

A.

Sheet index

B.

Cover sheet

C.

General notes

D.

Building code summary

What is a primary disadvantage in using the design-bid-build method?

A.

It attracts too many bidders

B.

All of the bids may exceed the owner's budget

C.

It requires a higher level of bid document quality

D.

It reduces the owner's control over the project during the construction phase

Which entity maintains project record documents?

A.

Architect/engineer (A/E)

B.

Contractor

C.

Owner

D.

Owner or A/E

During which stage of a facility's life cycle are operations and maintenance documents presented to the owner?

A.

After the authorities having jurisdiction issues a permit

B.

Closeout phase

C.

Preconstruction phase

D.

Construction phase

Under a single prime contract, shop drawings should be routed to the architect/engineer from whom?

A.

Contractor

B.

Material supplier

C.

Owner

D.

Subcontractor

Which team member is actively involved and interested in all phases of the project?

A.

Contractors

B.

Owners

C.

Architects/engineers

D.

Manufacturers/suppliers

When a public works project utilizes design-bid-build, which option would NOT minimize the risk of bid shopping?

A.

The architect/engineer/owner team can consider bid listing and bid depository provisions.

B.

Require bidders to provide a list of their intended subcontractors along with their bid.

C.

The subcontractor can withhold their prices from the bidder until the final moments before the deadline.

D.

The bidder can ask the subcontractor to reevaluate their prices to find a lower price after the subcontractor has submitted their price.

During the project closeout phase, what is an appropriate task for the facility manager?

A.

To ensure they have received the required spare parts, extra stock materials, and any necessary training needed in order to maintain the facility in the first year

B.

To coordinate with the architect a final clean-up and site restoration

C.

To hire a new security company to ensure maintenance and ground management

D.

To draft the final changes on the as-built documents