During an office renovation, a financial firm wants to continue occupying the space while maintaining daily functions. What is the BEST method for the designer to follow?

A.

Utilize fast-track scheduling for completion of the space as a whole

B.

Create separate permits for each area to be completed independently

C.

Designate one portion of the space to be completed prior to another beginning

In order for a building permit to be issued, what MUST be completed?

A.

demolition phase of project

B.

submission of contract documents

C.

final inspection by a building official

D.

issuance of the certificate of occupancy

How do project managers guide a project if they or the design team lacks expertise in a certain area?

A.

Find appropriate consultants and include them in the design team

B.

Use an appropriate consultant if a problem arises during the project

C.

Require project team members to research information on the design criteria

D.

Select one member of the design team to receive training in the expertise required

When does a project team gather information about a company’s culture, mission, values, and business goals to understand possible challenges for a new workplace environment?

A.

programming

B.

client interview

C.

schematic design

D.

design development

A residential client wants to build an addition that would occupy the entire side-yard. What is the interior designer responsible for checking before proceeding?

A.

soils report

B.

access route

C.

setback requirement

D.

neighborhood agreement

Which item causes the MOST issues when planning for systems workstations in an office space?

A.

The workstation cost is too expensive for the client’s budget

B.

The thickness of the panels was not considered when maintaining clearances

C.

The height of the panels is too low to reduce sound from traveling between workstations

D.

The electrical outlets are not maintained at the correct height to accommodate equipment

What is the MOST important consideration when specifying light fixtures for a retail store?

A.

Wattage

B.

Indirect glare

C.

Reflected glare

D.

Color rendering index

During a substantial completion walk-through, a designer notices that a door was installed incorrectly. What should the designer do NEXT?

A.

Meet with the general contractor, review the drawings, and schedule replacement

B.

Process a change order and include the new door location

C.

Add the door location and problem to the punch (deficiency) list

D.

Ask the client to accept the door, with a credit memo

A designer has a contract with a client to provide complete contract documents for a tenant build-out. Specifying FF&E is beyond the scope of the contract. The designer makes some general FF&E recommendations to show a systems furniture layout as required by the local code officials. The furniture comes in over the client’s previously undisclosed budget. What should the designer do?

A.

Suggest that the client purchase directly from the manufacturer

B.

Meet with the client and furniture provider to resolve the problems

C.

Research alternate furniture options to bring the budget back in line

D.

Let the client and the furniture provider work out the budget problems

Which of the following is part of an active system for fire protection?

A.

Area of refuge

B.

Means of egress

C.

Protected stairwells

D.

Pre-action sprinklers