During the design phase, drawings for ICT communications spaces should be reviewed for Standards compliance and

A.

cost projections.

B OSHA specifications

B.

client requirements

C.

equipment availability

A program manager is identifying and verifying risks as outlined in the risk management plan. The results will be recorded in which of the following?

A.

Risk register

B.

Risk monitoring and control

C.

Risk response planning

D.

Risk mitigation strategy

In a PTP network using optical fiber, the ________ is responsible for media conversions from the optical fiber to the balanced twisted pair network within the residence.

A.

ONU

B.

OS

C.

ONT

D.

OLT

E.

OLTS

Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?

A.

Program performance report

B.

Communications management plan

C.

Communications log updates

D.

Information gathering and retrieval system

Which of the following options BEST describes Request for Quote (RFQ)?

A.

Usually provides more detail involved with selecting the material, equipment, and components required during implementation (e.g. make, model, performance specifications)

B.

Can be submitted by the contractor in response to a field order or as an uninitiated request for a change in scope

C.

Used to obtain a formal response to the contract documents

D.

An invitation for the design professionals (e g, architect, engineer, consultant) or contractors to submit a proposal for services

A program completes all component projects and all identified benefits are being delivered However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters

To ensure the realization of long-term benefits what should the program manager use?

A.

Benefits register

B.

Benefits sustainment plan

C.

Benefits management plan

D.

Benefits transition plan

In a RFI, an ICT distribution designer instructs the contractor to test all the fibers In a PON Installation. Which of the following testing requirements does the designer include?

A.

Uni-directional 850 nm and 1300 nm

B.

Bi-directional 850 nm and 1300 nm

C.

Uni-directional 1310 nm and 1550 nm

D.

Bi-directional 1310 nm and 1550 nm

The new performance financial system is delivered lo all business entities on time following a one-year implementation program After six months of utilization the global finance department one of the main beneficiaries of the program, determines that quality and level of granularity of the financial data is not sufficient for them to analyze the key performance indicators (KPIs) defined Additionally, the global finance department is missing the analytical tools required to understand the causes of discrepancies

To address these shortcomings the global finance department submits a request for a follow-up initiative through the process defined by which of the following documents?

A.

Benefits sustainment plan

B.

Benefits governance plan

C.

Benefits realization report

D.

Benefits transition plan

Alter an organization initiates a strategic program several project managers express interest in joining the program Team. The program manager's supervisor recommends a list of project managers to be part of the team

What should the program manager do to select the project managers''

A.

Complete a skill set inventory and select the most suitable resource(s)

B.

Ask interested project managers for their CV or resume and conduct Interviews

C.

Accept the recommendation of the program manager's supervisor

D.

Contact the human resource manager tor project managers' availability

What's the RECOMMENDED twisted pair cable slack length to be left at the work area outlet location to enable the possibility of future changes in the Horizontal Cabling System?

A.

=0.152 m (0.5 ft)

B.

=0.3 m (1 ft)

C.

=1 m (3 ft)

D.

= 5m (16 40 ft)