A telephone facility and an electrical facility are required in a tunnel. To reduce the effects of EMI and eliminate the need for additional shielding of the cables, where would each facility be placed?

A.

On opposite sides of the tunnel

B.

On the same sides of the tunnel

C.

Together on the same pathway for easy access and maintenance

D.

One on the top part and one on the bottom part of the same side of the tunnel

E.

On the exterior of the tunnel

Which two of the following types of metallic conduit REQUIRE threaded couplings? (Select two options.)

A.

Electrical metallic tubing (EMT)

B.

Aluminum metal conduit (AMC)

C.

Flexible metal conduit (FMC)

D.

Intermediate metal conduit (IMC)

E.

Rigid metal conduit (RMC)

A regional finance program is impacted by a new currency regulation issued by a country in the region. The new regulation requires changes to the financial statements of that country's branches by the end of the fiscal year Failing to comply with the regulation may result in fines and/or closure of the branches. A branch general manager immediately meets with the program manager to select and secure a local fiscal expert to support the regulation as these types of resources are in high demand. There is a high risk that the changes will not be completed on time if the resource is not secured

What should the program manager do to address the risk?

A.

Build a coalition with local companies that can influence the government to renegotiate the imposed deadline

B.

Create fine and closure scenarios to assess the impact on the program and create a contingency plan

C.

Generate a delivery incentive contract with the selected fiscal expert to ensure on-time delivery of the revised financial statements

D.

Assess the risk incorporate it in the program's risk management plan and meet with the steering committee

An organization must accelerate a product to market. The program manager completes the preliminary program slaps and holds a kick-off meeting Project managers submit their preliminary schedules for review

What should the program manager do next?

A.

Assign resources lo the schedule and report the revised delivery date to the project managers

B.

Work with the project managers to refine the project schedules and deliverables to align with the program milestones

C.

Revise the project schedules to meet the program schedule and communicate to stakeholders

D.

Integrate the project schedules into the program schedule and report the revised delivery date to the project managers

The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B.

This is an example of which of the following?

A.

Program resource management planning

B.

Program risk mitigation

C.

Resource interdependency management

D.

Project resource planning

When designing horizontal pathways, the ICT distribution designer should consider the design's ability to (Select two options.)

A.

handle only the day one needs as the future is unknown.

B.

minimize occupant disruption when horizontal pathways are accessed.

C.

handle at least 3 different cabling media types.

D.

accommodate cabling changes

E.

accommodate at least 50 percent future growth

During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects What should the program manager do to address the situation'?

A.

Review and update the detailed stakeholder list

B.

Review and update the stakeholder engagement plan

C.

Execute the component project's communications management plan

D.

Update the risk register.

A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.

Which of the following deliverables captures these items?

A.

Program scope management plan

B.

Program governance plan

C.

Program scope statement

D.

Program work breakdown structure

In a program's definition phase a program manager in country A is assigned to expand a restaurant chain into country B. communications management plan zThe program manager creates the program team by identifying the required protect management resources

Which of the following represents an initial step needed to evaluate available resources that are aligned with me program's needs''

A.

Completing an assessment of skills and competencies

B.

Obtaining resource availability information from the functional managers

C.

Identifying program resource requirements

D.

Creating a program resource management plan

Conducted coupling may affect electronic devices primarily through which two of the following means'? (Select two options.)

A.

inductive coupling (by magnetic fields)

B.

Input signal lines

C.

Output signal lines

D.

Optical signal lines

E.

Capacitive coupling (by electric fields)