What type of redundancy provides two additional units, modules, paths, or systems in addition to the MINIMUM required to satisfy the base requirement.

A.

N

B.

N+1

C.

N+2

D.

2N

E.

2(N+1)

Within a data center, if you have dual path connectivity between the primary entrance room and secondary entrance room, in addition to dual connectivity between these two rooms and the main distribution and secondary distribution areas, what tier level would this infrastructure design represent?

A.

Tier I

B.

Tier II

C.

Tier III

D.

Tier IV

E.

Tier V

If you have a data center where the entire infrastructure must be completely shutdown on an annual basis to perform preventative maintenance and repair work, what tier level would this represent?

A.

Tier I

B.

Tier II

C.

Tier III

D.

Tier IV

If you are working on a physical security plan for a data center and focusing on building and access control, what layer of the plan would this relate to?

A.

Layer 1

B.

Layer 2

C.

Layer 3

D.

Layer 4

E.

Layer 5

What does ANSI/TIA 942 recommend as the MINIMUM height for overhead cable tray above finished floor within a data center?

A.

2.14 m (7 ft)

B.

2.44 m (8 ft)

C.

2.75 m (9 ft)

D.

3.05 m (10 ft)

E.

3.36 m (11 ft)

What is the air change requirement for a tunnel of 610 m (2000 ft) long with a diameter of 3.4 m (11 ft)?

A.

One complete air change per hour

B.

Two complete air changes per hour

C.

Three complete air changes per hour

D.

Four complete air changes per hour

E.

Five complete air changes per hour

Exhibit:

In this future marina layout, assuming that there are fewer than 10 slips being cabled, what would be the pre-cabling guideline to follow for terminal A?

A.

Installed one or two pair cables from the boat slips to a distribution terminal on the closest point of land.

B.

Place distribution cable onto the dock and terminate in a suitable cabinet or enclosure. Install service drop to each boat slip.

C.

Pre-cable each boat slip during construction.

D.

For security, each install should be terminated in the patch panel/cross-connect at the dockmaster or marina office.

Exhibit:

In this future marina layout, what would be the pre-cabling guideline to follow for the terminal A?

A.

Place distribution cable onto the dock and terminate in a suitable cabinet or enclosure. Run service drop to each boat slip.

B.

Provide one or two pair cables from the boat slips to a distribution terminal on the closest point of land.

C.

Pre-cable each boat slip during construction.

D.

For security, each run should be terminated in the patch panel/ cross-connect at the dockmaster or marina office.

What is the MINIMUM distance from the edge of a pool or other water hazards for a weatherproof enclosure?

A.

1 m (3 ft)

B.

2 m (7 ft)

C.

4 m (13 ft)

D.

6 m (20 ft)

E.

10 m (30 ft)

What is the MINIMUM clearance needed between the front of the telephone booth and any wall or fixture for most installations?

A.

300 mm (12 in)

B.

450 mm (18 in)

C.

610 mm (24 in)

D.

914 mm (36 in)

E.

2.4 m (8 ft)