Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

Which of the following is included in the business case section of a project charter?

A.

Scope of the project

B.

Details about the strategic reason for the project

C.

Problem statement

D.

Details about resource availability and allocation

Which of the following types of risk management is the most detailed type that focuses on addressing each separate and component-specific risk?

A.

Enterprise

B.

Process

C.

Operational

D.

Strategic

The following ANOVA table was developed for two factors, using a model that has no interaction term.

What is the value of the F statistic that should be used to determine whether Factor Y is statistically significant?

A.

0.83

B.

1.20

C.

3.26

D.

5.91

Which of the following tools would best be used to depict motion waste?

A.

Swim lane flowchart

B.

Spaghetti diagram

C.

Value stream map

D.

Backward tracing

A team calculates the value of a project in terms of the dollars saved and the costs avoided, and then compares that result with the amount of money spent to implement the project. This type of valuation is known as

A.

return on net assets

B.

return on investment

C.

net income

D.

general and administrative expenses

Displayed performance indicators is an example of

A.

control plans

B.

visual controls

C.

reliability-based maintenance

D.

a kanban system

Which of the following factors provides the most significant trade-off during tolerance design?

A.

Performance variation versus manufacturing cost

B.

Engineering cost versus manufacturing productivity

C.

Engineering schedule versus manufacturing schedule

D.

Program management cost versus manufacturing cost

A healthcare company is preparing to implement a new electronic medical records database system. The IT team has warned management about possible problems that could occur during and immediately after implementation, such as missing patient accounts, missing lab values, and incorrect medication order sets. Which of the following tools should management use to mitigate these risks?

A.

Failure mode and effects analysis

B.

Waste analysis

C.

Root cause analysis

D.

Pareto analysis

The Six Sigma problem-solving approach is appropriate for a project that

A.

focuses on the identification of wastes

B.

requires results in a week or less

C.

requires advanced statistical thinking

D.

has informal teams that manage the process

Based on the normal distribution shown, approximately what percentage of the data fall within one standard deviation of the mean?

A.

34%

B.

67%

C.

95%

D.

99.7%