In the context of the project organization, which of the following are classed as External Stakeholders by Agile?

    Regulatory Authorities

    Developers

    Customers

    Employees

A.

1, 2, 3

B.

1, 2, 4

C.

1, 3, 4

D.

2, 3, 4

What DSDM product describes how the benefits have actually accrued following a period in live operation?

A.

Prioritized Requirement List

B.

Benefits Assessment

C.

Project Review Report

D.

Delivery Plan

Which of the following statements about a 'Force Field Analysis' are true?

    It can reveal both barriers to overcome and possible sources of resistance.

    It should be created independently by the change manager.

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Why might the priority of a requirement in the Product Backlog differ from what might otherwise be shown?

A.

Different budget

B.

Different resources

C.

Different timeframe

D.

Different quality

What role is responsible for the delivery of the project from Foundations through to Deployment?

A.

Business Sponsor

B.

Business Visionary

C.

Project manager

D.

Technical Coordinator

Which practice provides an interactive environment in which all key players can contribute to the outcome?

A.

Modelling

B.

Facilitied Wordshop

C.

Iterative Development

D.

Timeboxing

During what DSDM phase is it established how quality to be assured?

A.

During Feasibility

B.

As part of Foundations

C.

At the start of Evolutionary Development

D.

During each timebox during Evolutionary Development

Which statement about change is correct for DSDM?

A.

Change is a symptom of an inability to define requirements properly

B.

Avoid change whenever possible

C.

Change is inevitable and males estimating very difficult

D.

Project operate with a changing world

Which approach is recommended for helping people through the 'change curve'?

A.

Actively involve line managers in listening and providing support.

B.

Recognize negative emotions as a sign that the change is being managed badly.

C.

Advise people not to discuss their problems with colleagues.

D.

Assume that everyone will eventually move on in time to deal with the change.

Which should always be the first step in the Continuous Change Management Cycle?

A.

Ideas.

B.

Prioritization.

C.

Discovery.

D.

Action.