Components of an organization's immediate industry and competitive environment include:

A.

political factors.

B.

interest rates.

C.

substitute products.

D.

sociocultural forces,

Which of the following risk management strategies assumes that losses in one part of the supplychain will be offset by gainsin another?

A.

Flexible

B.

Fluctuation

C.

Hedge 5

D.

Speculative

The production plan relates to a firm's financial planning because it is used to:

A.

calculate standard product costs.

B.

determine variable costs.

C.

project payroll costs.

D.

identify future cash needs.

Shop backlogs remain constant when:

A.

work input equals work output,

B.

forecasts are updated on the basis of the longest lead time item.

C.

capacity is assumed to be infinite.

D.

shop orders are released at a steady rate.

A company sold 8,400 units last year. Average inventory investment was $42,000. Whatwas the inventory turns ratio,knowing that the unit cost is $207?

A.

0.20

B.

0.25

C.

4

D.

5

Product X sells for $20 each, and it has a variable cost of $5 per unit. The company sells 10,000 units per year and has afixed cost of $120,000. What is the break-even point in units for Product X?

A.

6,000

B.

8,000

C.

10,000

D.

24,000

Adopting a lean approach to manage supply chain throughput rather than a more traditional approach means that:

A.

mare capacity may be required.

B.

less training may be required.

C.

more inventory may be required.

D.

longer cycle times may occur,

Providing a realistic basis for setting internal performance targets can be accomplished through:

A.

beta testing.

B.

benchmarking.

C.

breakthrough innovation.

D.

best practices.

Ergonomic workstation design should incorporate:

A.

an andon board.

B.

reduction of repetitive motion.

C.

bending so as to reduce monotony of work.

D.

visual systems.

A firm produces a moderate variety of products to stock in a single plant. The plant is organized in a functional layout withsome work cells. Which of the following indicators most appropriately would be used to evaluate the effectiveness of thedetailed capacity planning processes?

A.

Units of output per direct labor hour

B.

Change in level of work-in-process (WIP) inventory

C.

Percentage of master schedule attained

D.

Level of finished goods inventory