Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

Why should the Product Owner be present at the Daily Scrum?

A.

He/She doesn’t need to be there.

B.

To hear about impediments in functionality.

C.

To represent the stakeholders’ point of view.

D.

To participate as a Scrum Team member.

When does a Sprint conclude?

(choose the best answer)

A.

When the Product Owner decides enough has been delivered to meet the Sprint

Goal.

B.

When the Sprint Retrospective is complete.

C.

When all the tasks are completed by the Developers.

D.

When all Product Backlog items meet their Definition of Done.

Which answer best describes the topics covered in Sprint Planning? (Choose the best answer.)

A.

What to do and who will do it.

B.

How conditions have changed and how the Product Backlog should evolve.

C.

What can be done and how to do it, and why to do it.

D.

What went wrong in the last Sprint and what to do differently this Sprint.

E.

Who is on the team and what team member roles will be.

A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give?

A.

Product Backlog items must be estimated in story points.

B.

Estimates are made by the Development Team.

C.

Estimates must be in relative units.

D.

Scrum forbids estimating.

E.

Estimates are made by the Product Owner, but are best checked with the Development Team.

Who should make sure everyone on the Development Team does their tasks for the Sprint?

A.

The Project Manager.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Development Team.

E.

All of the above.

A Scrum Team is only allowed to meet with stakeholders during Sprint Review.

A.

True

B.

False

The Product Owner determines how many Product Backlog items the Development Team selects for a Sprint.

A.

False.

B.

True, accordingly to what was committed to the stakeholders.

C.

True, but only after confirmation by the resource manager that the Team has enough capacity.

D.

True.

E.

False, the Scrum Master does that.

F.

False, capacity and commitment are the Project manager’s responsibility.

A product Increment must be released to production at the end of each Sprint.

A.

True

B.

False

What does n mean tor a scrum Team to be cross-function at? (choose the best answer)

A.

The Scrum Team includes skilled individuals who together have all the skins necessary to create value each sprint

B.

Developers on the Scrum Team work closely with business analysis architects developers, and testers who are not on the team

C.

The Scrum Team includes not only developers but also business analysts, architects, and testers

D.

The Scrum Team is a virtual team drawing from separate teams of business analysts, architects, developers, and testers

When multiple Scrum Teams are working on a single product, what best describes the Definition of Done?

(choose the best answer)

A.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

When multiple Scrum Teams are working together on a product, they must mutually define and comply with the same Definition Of Done.

D.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.