The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

A.

Opportunities to insect and adapt the Sprint Backlog are lost.

B.

Impediments are raised and resolved more slowly.

C.

The Product Owner cannot accurately report progress to the stakeholders.

D.

Too much work is spent updating the Scrum board before the meeting.

E.

The Scrum Master loses the ability to update the Gantt chart properly.

F.

The Sprint plan may become inaccurate.

A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items “Done” by the end of the Sprint. Which three phrases best describe the purpose of a definition of “Done”? (Choose three.)

A.

It controls whether the developers have performed their tasks.

B.

It provides a template for elements that need to be included in the technical documentation.

C.

It creates transparency over the work inspected at the Sprint Review.

D.

It trucks the percent completeness of a Product Backlog item.

E.

It guides the Development Team is creating a forecast at the Sprint Planning.

F.

It defines what it takes for an Increment to be ready for release.

When must a Product Owner release each Increment? (Choose the best answer.)

A.

When it makes sense.

B.

When the Scrum Team finishes their work.

C.

Whenever the product is free of defects.

D.

After every Sprint, Without exception.

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum?

(choose the best two answers)

A.

Identification of impediments that may prevent the Developers from achieving the Sprint Goal.

B.

An update of completed tasks and of the remaining work so the Scrum Master

can plan the next day.

C.

An updated Scrum board to make Sprint progress transparent for the

stakeholders.

D.

A shared understanding of the most important work to be undertaken next to

achieve the best possible progress toward the Sprint goal.

E.

A status report for the upper management indicating what each individual has done, will be doing, and what is impeding him/her.

The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog.

A.

True

B.

False

What is the key concern when multiple Development Teams are working from the same Product Backlog?

A.

Minimizing dependencies between teams.

B.

Clear definition of requirements.

C.

Meeting original scope projections.

D.

Making sure there’s enough work for everyone on every team.

E.

Maximizing velocity.

How do you know that a Development Team is cross-functional?

A.

Development Team has all the skills to create a potentially releasable increment by the end of every Sprint.

B.

A few of the Development Team members pair program and do Test Driven Development.

C.

There are no conflicts within the Development Team.

D.

Every member of the Development Team is able to perform every task.

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update management on what is being worked on.

D.

Answer QUESTION NO:s from the Development Team about items in the current Sprint.

Who is responsible for the sizing of Product Backlog items?

(choose the best answer)

A.

The Developers after clarifying requirements with the Product Owner

B.

The Scrum Master.

C.

The Product Owner with input from the Developers.

D.

The Developers, alone.

E.

The most senior people in the organization, including architects and subject matter experts.

When does the second Sprint start?

A.

Once the architectural changes for the second Sprint have been approved by the senior architect.

B.

After the Product Backlog for the second Sprint has been selected.

C.

Immediately after the first Sprint.

D.

After the customer completes acceptance testing of the first Sprint.