Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?

A.

When several operations are maintained for one product

B.

When alternative resources are used within one operation

C.

When several production versions are maintained for one product

D.

When multiple planned orders are scheduled in parallel on one resource

What will happen in the MRP run if you have created a new MRP-relevant material that supports both in-house production and external procurement?

A.

The MRP run assumes external procurement.

B.

The MRP run assumes in-house production.

C.

The MRP run plans the material only if a quotation has been maintained.

D.

The MRP run does NOT consider the material; it has to be planned interactively.

What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.

A.

Planned order

B.

Scheduling agreement schedule line

C.

Production order

D.

Purchase order

How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.

A.

By capacity planning

B.

By order confirmation

C.

By order release

D.

By mass processing

During production order creation, several valid production versions are found. How does the system choose the production version?

A.

Alphanumeric or quota arrangement

B.

Planned order or material number

C.

Validity period or sales order

D.

Lot size or material cost

Which of the following automation options can you use for production orders? Note: There are 2 correct answers to this question.

A.

You can use trigger points to automatically create rework orders via confirmations.

B.

You can use mass processing to set production orders to technically complete.

C.

You can use the production scheduling profile to automatically set orders to technically complete.

D.

You can use mass processing to read PP master data for production orders.

Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

A.

To simplify the structure of bills of material

B.

To reduce the number of changes required in bills of material

C.

To reduce the number of material masters

D.

To make the assignment of components easier

E.

To increase the number of planning levels

What is a work center hierarchy?

A.

A group of alternative work centers for production structured in hierarchy levels by priorities

B.

A group of alternative work centers providing a cumulative available capacity for production

C.

A group of work centers in a production line being used in sequence for production

D.

A group of work centers in a parallel sequence that is used to split production quantities and work on them in parallel

What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.

A.

You can reschedule the operation using lead time scheduling.

B.

You can reschedule the operation using infinite scheduling in a planning table.

C.

You can reschedule the operation using finite scheduling in a planning table.

D.

You can reschedule the operation in the Manage Work Center Capacity app.

Which options do you have to plan both quantities and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.

A.

Assign planned orders manually in the planning table.

B.

Run MRP with quota arrangement.

C.

Run MRP with automatic selection of production version.

D.

Run PP/DS heuristics for repetitive manufacturing.