What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm In a project management project?

NOTE: There are 3 correct answers to this question.

A.

Accounting integration for this project is active

B.

The project type must allow time recording with the CATS

C.

The role type must allow time recording with CATS

D.

The planned effortsis on the task

What is the PR/PLAN_INI_PREP report used for?

A.

To create financial and capacity categories and groups based on customizing

B.

To upload financial data from Microsoft Excel

C.

To transfer costs from accounting objects to PPM

D.

To transfer recoded time from CATS to PPM

You have created a role in project management but the role is not displayed on the fast entry screen.

What could be the reason for this?

A.

The flexible Assignment indicator is active in role type customizing

B.

The role has the staffing in preparation status

C.

The role has the staffing in process status

D.

The Distribution indicator is active role type customizing

You have defined an item template. When you create a new item, you notice that you cannot select the template.

What could be the reason for this?

NOTE: There are 2correct answers to this question

A.

The item template is not available in the selected bucket

B.

The item template has the Activate status

C.

The item template has a different item type

D.

The item template start date is in the future

What can you define in the item template?

A.

Category

B.

Link to a project management project

C.

Sequence of decision points

D.

Financial planning

You staff a resource to a project.

Where is the default authorization for the resource defined?

A.

In the project

B.

In the project template

C.

In customizing for role functions

D.

In customizing for role types

Which customizing activity do you use to integrate capacity planning of an item with financial planning?

A.

Define financial integration scenarios

B.

Define portfolio type

C.

Define financial and capacity views

D.

Define financial planning settings

Which information can be assigned to a business partner in project management?

NOTE: There are 3 correct answers to this question

A.

Work centers

B.

Areas and locations

C.

Personal numbers

D.

Production resources or tools (PRT)

E.

SAP users

What data can you synchronize between a portfolio item and an initiative using Decision Flow management?

A.

Documents

B.

Notes

C.

Metrics

D.

Development Cost

You want to confirm your work hours to tasks with the cross-Application time sheet (SAP CATS). When you enter the time sheet (CAT2) your list is empty.

What could be the reason for this?

NOTE: There are2correct answers to this question.

A.

Your role and business partner are assigned to task that have the created status

B.

Your role and business partner are assigned to tasks that have the in process status

C.

Your personal number is not assigned to a business partner

D.

Your user is not assigned to a business partner