Which non-PPM function is often provided by a P3O in the interests of business efficiency?

A.

Challenging project data

B.

Scrutinising the impact of project delivery on business as usual

C.

Escalating risks and issues

D.

Providing a secretariat service to management boards

Which is a functional area within a P3O model?

A.

Hub Portfolio Office connected by spokes

B.

COE functions or services

C.

Virtual Office

D.

Flexible resource pool

Which of the following statements about how a P3O should integrate with the wider organization are true?

1. Operates independently of other functions within the organization

2. Typically relies on dedicated full-time resources to provide financial functions needed

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 is true

Which of the following are key responsibilities of the Portfolio Analyst role?

1. Balance the portfolio in terms of strategic change against business as usual

2. Make recommendations on an appropriate programme/project balance

3. Provide a fast-track programme mobilization support service

4. Highlight problems relating to project interdependencies

A.

1,2,3

B.

1,2,4

C.

1,3,4

D.

2,3,4

Which is a benefit of the portfolio prioritization and optimization technique?

A.

Highlights programme issues requiring intervention

B.

Documents repeatable processes enabling increased PPM maturity

C.

Provides resource capacity to the portfolio when required

D.

Supports senior management investment decisions by aligning programmes to strategy

Which of the following describe the governance responsibilities of a P3O model?

1. Provides the governance and control backbone for an organization's change initiatives

2. Provides a single source for all data relating to the organization's change initiatives

3. Implements rules for decision-making relating to programmes and projects

4. Makes decisions on behalf of the main board

A.

1,2,3

B.

1,2,4

C.

1,3,4

D.

2,3,4

Which of the following are key stakeholders in a temporary Project Office?

1. Organization Portfolio Office

2. Business as usual staff

3. Suppliers to the project

4. Project Board members

A.

1,2,3

B.

1,2,4

C.

1,3,4

D.

2,3,4

What does a P3O provide to support the principle 'govern effectively'?

A.

Coaching and training to P3O roles

B.

Independent gated review coordination and assurance

C.

A benefits tracking service to business owners

D.

A fast track mobilization service to programmes and projects

Which is NOT an objective of a programme?

A.

Coordinate related projects and activities

B.

Deliver business products according to a Business Case

C.

Deliver outcomes and benefits

D.

Align to strategic objectives

Which of the following statements about the return of internal resources to an operational role when closing a temporary Programme Office are true?

1. Feedback to the line manager should be given on performance

2. Staff members will be reluctant to return if they are to lose status

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 is true