A company CEO issues a mandate to automate a new-client onboarding process to replace manual and paper-based procedures. After the program sponsor and program manager obtain formal acceptance of the program charter, what should be done next?
You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?
Your program has just been chartered during the program initiation process. Your program also needs to create three program statements. Which program statement defines how your program will manage tradeoffs, competing objectives, and program and organization decisions?
A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk.
What should the program manager do to monitor and control the supplier?
Alice is the project manager of the NHQ Project and is entering the project's closing processes. The project, she has managed, has been for another organization in a contractual relationship. Her organization requires Alice to complete performance reviews of the project team, review the deliverables with the project customer, and to obtain formal signoff of the project deliverables. There may be other conditions and activities that Alice likely will need to do in this final project phase. Where can Alice check regarding this project?
Your program creates a byproduct that you could sell to a client. The cost of the byproduct would offset the cost of the program by nearly $7,500 per month. This is an example of which positive risk response?
A program with 10 components is in the planning phase. Project managers who oversee the component projects request detailed schedules. These schedules will be merged into one document to create a master schedule.
What should the program manager do to ensure that the overall program life cycle will meet stakeholder needs and deliver planned benefits?
A program with objectives that impact a large segment of the population receives negative commentary from organizations representing the public interest.
What action should the program manager take first?
What does RACI stand for?
A program has been established and preparation is complete.
Component projects are planned as a part of which of the following?