You are managing a portfolio for your company and are trying to balance the tasks that will be done internally based on the availability and the ones that will be outsourced. Managing supply and demand is a recurring activity in the portfolio life cycle and results in changes in resource utilization and resource efficiency. Where is this type of results normally found?
Assume you are putting together for the Portfolio Review Board several options for consideration of potential components and current components. You are using an approach with different probabilities to determine outcomes and EMV. Which of the following would you recommend realizing Components A and B are new, while C and D are in progress:
Assume you are a functional manager in your medical device company in research and development. Your scientists have determined a new product that will be a breakthrough for the company, and you want to serve as the sponsor for this component and present it to your Portfolio Review Board. You will need resources from other parts of the company to commercialize it. As you prepare your proposal you are following the key descriptors set up by the portfolio staff and will include:
Your organization, a leading restaurant focusing on pancakes, is seeking to expand its portfolio. It is interested in ensuring new components support: return on investment, customer satisfaction, reputation enhancement, and branding. These four areas represent:
While a variety of prioritization approaches are available and are useful in portfolio management and many software packages support the various approaches, it is important to recognize:
You have been managing a complex portfolio for the banking industry and it is sought to be the shifting to the top-notch digital banking era for one of the major international banks. You know you will have changes along the lifecycle and you plan to manage them correctly in order to maintain alignment and correct execution. If you need to reflect changes based on cost, requirements, and schedule. To which of the following section in the portfolio management plan will you refer?
You have finalized optimizing your portfolio and want to avoid any delay by directly recommending the initiation of multiple portfolio components. What do you need for starting this?
You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risks is key to success, and you are coaching your team on the same. While planning for risk management, multiple investment choice tools are used as part of the quantitative and qualitative analyzes. Which of the following tools determines the effects of portfolio velocity?
Calculate the composite index for the following portfolio having CPI weight = 80% and SPI weight = 20%
Larger image
The governance board has an integral part in the realization of the portfolio strategic value. In your opinion as a portfolio manager, Governance board decisions are based on