Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:

If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?

A.

The project will complete on time.

B.

The project will be late by one day.

C.

The project will be late by two days.

D.

The project will be early by two days.

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You reviewed these activities with your project team and discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You elect to create a new schedule for the project. What project Management process are you working with when you create a new target schedule?

A.

Develop schedule

B.

Estimate activity durations

C.

Control schedule

D.

Estimate activity resources

Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vendor, the project is going well. What should Billy report as her schedule performance index for this project?

A.

1.23

B.

100 percent because the vendor caused her lateness

C.

.80

D.

$524,000

You work as a project manager for BlueWell Inc. According to you, which of the following is an output of the Sequence Activities process?

A.

Project scope statement

B.

Project schedule network diagram

C.

Activity list

D.

Organizational process assets

You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in the figure:

Based on this diagram, find out the earliest day on which Activity G can be started.

A.

Day 13

B.

Day 7

C.

Day 22

D.

Day 17

You work as a scheduler for your organization. You are developing a schedule and its constraints for the SAP project. There are nine inputs to develop a project schedule. Which of the following is NOT an input to the schedule development process?

A.

Work breakdown structure

B.

Activity attributes

C.

Resource calendars

D.

Activity list

You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some doubts about the inputs of the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in project communication management?

A.

Expert judgment

B.

Project charter

C.

Stakeholder analysis

D.

Stakeholder register

You work as a project manager for BlueWell Inc. Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team?

A.

Project Schedule Management Plan

B.

Project Staffing Management Plan

C.

Project Human Resources Management Plan

D.

Project Communications Management Plan

Frank is the project manager of a construction project. In this project, Frank has elected to allow the interior design phase of the project to overlap with the pool construction phase of the project. Normally, Frank would not allow these two phases to overlap, but for this project, he has elected to do so in order to compress the project schedule. What is this schedule compression technique called?

A.

Resource leveling heuristic

B.

Lead time

C.

Fast tracking

D.

Crashing

Andy is the project manager for his project. Andy and his project team are identifying stakeholders who can significantly impact the project, what the level of participation for each identified stakeholder may be, and classifying the stakeholders by common characteristics, concerns, and their perception of the project. Andy and his project team want to define an approach as a result of this information to gain support from the stakeholders for their project. What should Andy and his project team create in this scenario?

A.

Stakeholder assessment information

B.

Stakeholder register

C.

Communications management plan

D.

Stakeholder management strategy