Halloween Sale Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: estly75

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

A.

Decomposition

B.

Inspection

C.

Project analysis

D.

Document analysis

Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:

A.

Level of control.

B.

Communication channels.

C.

Scope.

D.

Strategic alignment.

The following chart contains information about the tasks in a project.

question 108

Based on the chart, what is the schedule performance index (5PI) for Task 4?

A.

0.83

B.

0.9

C.

1.11

D.

1.33

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

A.

portfolio

B.

program

C.

selection

D.

sub portfolio

Power, urgency, and legitimacy are attributes of which stakeholder classification model?

A.

Salience

B.

Influence/impact

C.

Power/interest

D.

Power/influence

The following chart contains information about the tasks in a project.

question 111

Based on the chart, what is the cost performance index (CPI) for Task 2?

A.

0.8

B.

1

C.

1.25

D.

1.8

An output of the Perform Integrated Change Control process is:

A.

Deliverables.

B.

Validated changes.

C.

The change log.

D.

The requirements traceability matrix.

Analytical techniques are a tool and technique of which process in Project Procurement Management?

A.

Plan Procurement Management

B.

Control Procurements

C.

Conduct Procurements

D.

Close Procurements

Which type of graphic is displayed below?

question 114

A.

Work breakdown structure

B.

Context diagram

C.

Control chart

D.

Pareto diagram

An example of a group decision-making technique is:

A.

nominal group technique

B.

majority

C.

affinity diagram

D.

multi-criteria decision analysis

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

A.

Internal

B.

External

C.

Discretionary

D.

Mandatory

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

A.

Validate Scope.

B.

Plan Scope Management.

C.

Control Scope.

D.

Define Scope.

The chart below is an example of a:

question 118

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Which project risk listed in the table below is most likely to occur?

question 119

A.

1

B.

2

C.

3

D.

4

The following is a network diagram for a project.

question 120

The critical path for the project is how many days in duration?

A.

10

B.

12

C.

14

D.

17