Which of the following relationships is rarely used in PDM (Precedence Diagramming Method)?

A.

Start-to-Finish

B.

Finish-to-Start

C.

Start-to-Start

D.

Finish-to-Finish

In which of the following organizations the project manager role is likely to be part-time?

A.

Weak matrix

B.

Functional

C.

Balanced matrix

D.

Both A and B

A risk response which involves eliminating a threat is called ________.

A.

Mitigation

B.

Deflection

C.

Avoidance

D.

Transfer

Formal acceptance by the client or sponsor of the project should be prepared and distributed during which process?

A.

Distribute Information

B.

Administrative Closeout

C.

Organizational Planning

D.

Report Performance

Which of the following is true about procurement documents?

A.

Procurement documents are used to solicit proposals from prospective sellers.

B.

Invitations for Bid and Request for Proposal are two examples of procurement documents.

C.

Procurement documents should be structured to facilitate accurate and complete responses from prospective sellers.

D.

Al1 of the above

Which of the following can generate a milestone list?

A.

Define Activities

B.

Sequence Activities

C.

Estimate Activity Resources

D.

Estimate Activity Durations

What percentage of sales is estimated to be the cost of non-quality?

A)0 3-5%

B. 12-20%

C. 30-40%

D. 6"8%

Your project is moving ahead of schedule. Management elects to incorporate additional quality testing into the project to improve the quality and acceptability of the project deliverable. This is an example of which one of the following?

A.

Scope Creep

B.

Change Control

C.

Quality Assurance

D.

Integrated Change Control

Which of the following is not a process of project human resource management?

A.

Organizational Planning

B.

staff Acquisition

C.

Distribute Information

D.

Team Development

When a risk should be avoided?

A.

The risk event has a low probability of occurrence and low impact.

B.

The risk event is unacceptable - generally one with a very high probability of occurrence and high impact.

C.

It can be transferred by purchasing insurance.

D.

A risk event can never be avoided.

Which of the following statements concerning bottom-up estimating is true?

A.

The cost and accuracy of bottom-up estimating is driven by the size of the individual work items.

B.

Smaller work items increase both cost and accuracy.

C.

Larger work items increase both cost and accuracy.

D.

Both A and B are true

Which of the following is best for handling cross-functional project needs for a large, complex project?

A.

A strong matrix organization

B.

A project coordinator

C.

A project expediter

D.

Direct executive involvement

Which of the following are inputs that belong to Estimates Activity Resources?

A.

Activity List

B.

Resource Calendar

C.

Activity Attributes

D.

All of the above are inputs of Estimates Activity Resources

Completion of a product scope is measured against which of the following:

A.

WBS and WBS Dictionary

B.

Product Requirements

C.

Project Management Plan

D.

Product Management Plan

If a project has an 80% chance of having the scope defined by a certain date and a 70% chance of obtaining approval for the scope by a certain date, what is the probability of both events occurring?

A.

75%

B.

65%

C.

50%

D.