Which of the following processes are within the Initiating Process Group?

A.

Develop Project Management Plan and Identify Stakeholders

B.

Develop Project Management Plan and Plan Communications

C.

Develop Project Charter and Identify Stakeholders

D.

Develop Project Charter and Develop Project Scope Statement

Project Management Process Groups are linked by:

A.

the outputs they produce

B.

discrete or one-time events

C.

the project management plan

D.

common tools and techniques

Which of the following can be used as an input for Define Scope?

A.

Product analysis

B.

Project charter

C.

Scope baseline

D.

Project scope statement

Analytical techniques are a tool and technique of which process in Project Procurement Management?

A.

Plan Procurement Management

B.

Control Procurements

C.

Conduct Procurements

D.

Close Procurements

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

Which of the following is the correct network diagram for the table?

A.

Begin-A-C-D-E-End-B-D

B.

Begin-A-B-C-D-E-End

C.

Begin-A-B-D-E-End A-C-D

D.

Begin-A-C-D-E-End-B-C

A Pareto chart is a specific type of:

A.

control chart

B.

histogram

C.

cause-and-effect diagram

D.

scatter diagram

Which tool or technique is used to develop the human resource management plan?

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

What scope definition technique is used to generate different approaches to execute and perform the work of the project?

A.

Build vs. buy

B.

Expert judgment

C.

Alternatives identification

D.

Product analysis

What is the lowest level in the Work Breakdown Structure called?

A.

Work Packages

B.

Activities

C.

Schedules

D.

Tasks

Which of the following types of a dependency determination is used to define the sequence of activities?

A.

Legal

B.

Discretionary

C.

Internal

D.

Resource

The run chart created during the Perform Quality Control process on a project is used to show the:

A.

relationship between two variables

B.

data points plotted in the order in which they occur

C.

most common cause of problems in a process

D.

frequency of occurrence

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

A.

Control Schedule.

B.

Quality Control.

C.

Perform Integrated Change Control.

D.

Develop Schedule.

Which tool or technique is effective in a project in which the deliverable is not a service or result?

A.

Inspection

B.

Variance analysis

C.

Decomposition

D.

Product analysis

When would resource leveling be applied to a schedule model?

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

Which of the following makes changes to formally control documentation to reflect modified or additional ideas or content?

A.

Defect repair

B.

Updates

C.

Corrective action

D.

Performance reports

The project manager needs to review the templates in use. The templates are part of the:

A.

Enterprise environmental factors.

B.

Historical information,

C.

Organizational process assets.

D.

Corporate knowledge base.

Which of the following is an input to Direct and Manage Project Execution?

A.

Performance reports

B.

Project charter

C.

Outputs from planning processes

D.

Enterprise environmental factors

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

A.

$50

B.

$100

C.

$125

D.

$200

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

A.

Utilize the change control process.

B.

Crash the schedule to fix the defect.

C.

Leave the defect in and work around it.

D.

Fast-track the remaining development.