When setting up capitalization options on a project type, you have decided to enable the Require Complete Asset Definition option. If this option is enabled, the "Transfer Assets to Oracle Fusion Assets" process will place asset lines with complete definition into which queue in Oracle Fusion Assets?

A.

New

B.

Hold

C.

Posted

D.

Post

Shift is one of the key elements in defining project and resource calendars.

Which two additional key elements are required to define the project and resource calendars? (Choose two.)

A.

Schedule Exceptions

B.

Workday Patterns

C.

Time off

D.

Expenditure Type

E.

Accounting Calendar

Which component provides a human workflow service that handles all interactions with users or groups in business processes?

A.

Security Console

B.

SOA Suite

C.

Subledger Accounting

D.

BPM Worklist

Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio Management and Oracle Project Portfolio Management Cloud. (Choose three.)

A.

Event completion flowsfrom Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.

B.

Billing events flow from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.

C.

Summarized actual quantity and cost flowfrom Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.

D.

Projects and task definitions flowfrom Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.

E.

Project plans and progress flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.

As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes in HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers. (Choose the best answer.)

A.

Pool Membership

B.

attributes that the project enterprise resources are assigned after creation

C.

Jobs

D.

Person Type

Identify thethreecontract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)

A.

Expenditure Type

B.

Projects

C.

Contract Line

D.

Contract Header

E.

Task

Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types. Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)

A.

Create a revenue method with a revenue method classification of Amount Based.

B.

Create a revenue method with a revenue method classification of Rate Based.

C.

Create a revenue method classification with a revenue method of Percent Spent.

D.

Create a revenue method classification with a revenue method of Percent Complete.

Your organization has a requirement to retrieve the value of the cost center segment based on the department.

Which source can you use while defining the account rule to achieve this requirement?

A.

Project Organization Cost Center Segment

B.

Expenditure Business Unit Cost Center Segment

C.

Event Organization Cost Center Segment

D.

Expenditure Organization Cost Center Segment

Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client's expectations. Identify two valid rules based on which cost association works. (Choose two.)

A.

If one branch contains a user-defined resource type, precedence is given to the branch that contains a user-defined resource type.

B.

If a transaction maps to more than one level, Oracle PPM Cloud sums the precedence numbers for all resource type in the branch and gives precedence to the resource element in the branch with the highest sum.

C.

If there is only one level in RBS to which the transaction maps, the cost amounts are mapped to that level.

D.

If the sum of precedence numbers is the same for more than one branch, precedence is given to the branch with thelowest number at the lowest level.

Which product offering enables you to collaboratively plan and deliver projects by leveraging intuitive and integrated scheduling tools?

A.

Resource Management

B.

Project Control

C.

Project Management

D.

Project Costing