What part of defining the business needs process will evaluate the ends that the organization is seeking to achieve?

A.

Business goals and objectives

B.

Alternative identification

C.

Solution assessment

D.

Requirements

Jane is the business analyst for her organization and she is completing passive observation to identify improvement opportunities in the workflow. She notices that some of the employees perform certain customer- facing activities in a different format than the other workers.

Is this a problem that can be addressed as part of an improvement opportunity?

A.

It can be a problem as customers could become confused or frustrated because of the different approaches to the work.

B.

It is not a problem unless there is a drop in sales so it should be left alone.

C.

It can be a problem as the enterprise environmental factors always call for consistency in all processes.

D.

It is not a problem unless the customer complains. If Jane has not noticed the customers complaining then the process should be left along.

What is the term used to describe the cost of the solution after the solution has been implemented in production by a vendor?

A.

Total ownership costing

B.

Lifecycle maintenance fees

C.

Sustainability fees

D.

Total cost of ownership

Fred's organization is using a plan-driven approach for the business analysis deliverables.

In this approach how will the requirements be captured?

A.

Fred will use the appropriate documentation at the discretion of the business analysis team.

B.

Fred will use the project management information system.

C.

Fred will use whatever business analysis forms are most appropriate.

D.

Fred will use standardized templates.

You are the business analyst for your organization. You are preparing the business needs documentation for a new solution to an identified problem. Parts of your input for this process are the business goals and

objectives set by your organization.

What approach can you use to assess the business goal and their validity and longevity?

A.

Functional decomposition

B.

POLDAT

C.

SMART

D.

Root cause analysis

When is stakeholder analysis performed?

A.

As soon as the project charter is created.

B.

As soon as the project sponsor is named.

C.

As soon as a business need is identified.

D.

As soon as a business solution is identified.

You are the business analyst for your organization and you are completing the manage requirements traceability process. You are tracking the requirements to determine how the requirements are interrelated with one another and with the actual delivery of the project scope.

There are actually three reasons why the business analyst should trace requirements.

Which one of the following is not one of the three reasons why trace requirements is useful?

A.

Impact analysis

B.

Requirements coverage

C.

Requirements allocation

D.

Quality control

You are the business analyst for your organization. On your current project you'll be using the change-driven approach for defining requirements and gathering feedback.

Which of the following statements best describes the change-driven approach?

A.

The change-driven approach favors defining requirements through experimentation.

B.

The change-driven approach does not define the requirements until after a solution for the problem has been identified.

C.

The change-driven approach favors defining requirements standardized templates.

D.

The change-driven approach favors defining requirements through team interaction.

What plan includes the description of the scope of work, the deliverable Work Breakdown Structure, the activity list, and estimates for the business analysis activities?

A.

Project management plan

B.

Implementation plan

C.

Requirements management plan

D.

Business analysis plan

Which of the following is concerned with determining whether the information used for risk analysis is probable, of high class, or accurate?

A.

Risk Urgency Assessment

B.

Risk Probability and Impact Assessment

C.

Risk Categorization

D.

Risk Data Quality Assessment