Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exc65

An organization has a mature control environment but limited internal audit resources Given this scenario, on which of the following should the internal auditors focus their testing?

A.

Detective compensating controls

B.

Preventive compensating controls

C.

Detective Key controls

D.

Preventive key controls

According to IIA guidance, which of the following objectives was most likely formulated for a non-assurance engagement?

A.

The internal audit activity will assess the effects of changes in maintenance strategy on the availability of production equipment

B.

The internal audit activity will inform management on the possible risks of moving the data warehouse to a cloud server maintained by a third party.

C.

The internal audit activity will ascertain whether the data center security arrangements are compliant with agreed terms

D.

The internal audit activity will ensure equipment downtime risks have been managed in accordance with the internal policy.

Which of the following statements best explains why an internal auditor should pay attention to retained earnings of an organization?

A.

Retained earnings indicate the amount of potential dividends to be paid out to new investors.

B.

Retained earnings represent the amount of excess cash available in the organization.

C.

Retained earnings demonstrate that the organization was able to generate working capital from its own activities.

D.

Retained earnings constitute the main criterion used by ratings agencies to assess an organization.

An internal audit team leader is having difficulties completing the planning phase of an assurance engagement because the business unit lacks a system of internal controls. Which of the following is the most appropriate course of action for the internal audit team leader?

A.

Defer the engagement until a system of internal control has been established

B.

Change the scheduled engagement from assurance to consulting to help correct the shortcomings

C.

Add a consulting component to the already scheduled assurance engagement

D.

Seek the involvement of the external auditor to assist with improving the internal controls

During the planning stage of an assurance engagement, an internal auditor has been assigned to prepare a risk matrix. Which of the following should the internal auditor consider when attempting to identify process-level risks?

A.

Possible tests

B.

Possible scenarios

C.

Possible controls

D.

Possible samples

An internal auditor has discovered that duplicate payments were made to one vendor Management has recouped the duplicate payments as a corrective action Which of the following describes managements action in this case?

A.

A condition-based action plan

B.

A cause-based action plan.

C.

A root cause-based action plan.

D.

An effect-based action plan.

Which of the following is not a primary purpose for conducting a walk-through during the initial stages of an assurance engagement?

A.

To help develop process maps.

B.

To determine segregation of duties.

C.

To identify residual risks.

D.

To test the adequacy of controls.

According to IIA guidance, which of the following procedures would be least effective in managing the risk of payroll fraud?

A.

The employee’s name listed on organization’s payroll is compared to the personnel records.

B.

Payroll time sheets are reviewed and approved by the timekeeper before processing.

C.

Employee access to the payroll database is deactivated immediately upon termination.

D.

Changes to payroll are validated by the personnel department before being processed.

An internal auditor s testing tor proper authorization of contracts and finds that the rate of deviations discovered in the sample is equal to the tolerable deviation rate. When of the following is the most appropriate conclusion for the internal auditor to make based on this result?

A.

The internal auditor concludes that management may be placing undue reliance on me specified control

B.

The internal auditor concludes that the specified control is more effective than it really is.

C.

The internal auditor concludes that the specified control is acceptably effective

D.

The internal auditor concludes that additional testing will be required to evaluate the specified control

Which of the following is an inherent risk of issuing an opinion on the overall effectiveness of internal control?

A.

The results of individual engagements do not support a satisfactory opinion on the effectiveness of internal control.

B.

The results of the individual engagements do not support a positive assurance opinion on the effectiveness of internal control

C.

The audit risk and associated legal implications increase

D.

The reliance on other assurance providers increases

A bicycle manufacturer incurs a combination of fixed and variable costs with the production of each bicycle. Which of the following statements is true regarding these costs?

A.

if the number of bicycles produced is increased by 15 percent, the variable cost per unit will increase proportionally

B.

The fixed cost per unit will vary directly based on the number of bicycles produced during the production cycle.

C.

The total variable cost will vary proportionally and inversely with the number of bicycles produced during a production run.

D.

if the number of bicycles produced is increased by 30 percent, the fixed cost per unit will decline.

According to IIA guidance, which of the following objectives was most likely formulated for a non-assurance engagement?

A.

The internal audit activity will assess the effects of changes in maintenance strategy on the availability of production equipment.

B.

The internal audit activity will inform management on the possible risks of moving the data warehouse to a cloud server maintained by a third party.

C.

The internal audit activity will ascertain whether the data center security arrangements are compliant with agreed terms.

D.

The internal audit activity will ensure equipment downtime risks have been managed in accordance with internal policy.

The internal audit activity is currently working on several engagements, including a consulting engagement on the management process in the human resources department. Which of the following actions should the chief audit executive take to most efficiently and effectively ensure the quality of the engagement?

A.

Assign an experienced manager to monitor the whole engagement process.

B.

Employ fieldwork peer review to enhance the work quality.

C.

Require internal auditors to follow a standardized work program.

D.

Personally supervise the engagement

An internal auditor wants to determine whether employees are complying with the information security policy, which prohibits leaving sensitive information on employee desks overnight. The auditor checked a sample of 90 desks and found eight that contained sensitive information. How should this observation be reported, if the organization tolerates 4 percent noncompliance?

A.

The matter does not need to be reported, because the noncompliant findings fall within the acceptable tolerance limit.

B.

The deviations are within the acceptable tolerance limit, so the matter only needs to be reported to the information security manager.

C.

The incidents of noncompliance fall outside the acceptable tolerance limit and require immediate corrective action, as opposed to reporting.

D.

The incidents of noncompliance exceed the tolerance level and should be included in the final engagement report.

An internal auditor is tasked with evaluating the adequacy of the organization's inventory fraud controls. What is the most relevant information that the auditor can obtain from the documentation of cyclic counting for this purpose?

A.

Accounting adjustments of inventories are approved by the management in accordance with a signature policy

B.

Root causes of inventory differences are analyzed and corrective measures are followed

C.

High value items are inventoried more frequently throughout the year

D.

Value of accounting adjustments matches with the value of inventory differences and are made in a timely manner