When defining the task duration, you can do it in...

A.

Days

B.

Hours

C.

Fractions

D.

All of these are possable

Looking at the below image, when would you expect to work on the Create Instructor Guide task (WBS 2.4) by looking at the Dependency column?

A.

Cannot start until Approve Student Guide finishes

B.

Cannot start until Approve Student Guide starts

C.

Cannot start until Create Slides finishes

D.

Cannot finish until Create Slides finishes

What roles are authorized to create programs?

A.

Only Program Leads and External Program Leads

B.

Any role

C.

Program designers only

D.

Project leads only

What is the maximum character length for the name of a Program?

A.

64

B.

127

C.

264

D.

Unlimited

When you promote a project to the Assign state, what happens to the WBS tasks?

A.

They are automatically promoted to the Assign state

B.

They are unchanged

C.

They are assigned to the Active state

D.

They are ready to be manually promoted

When creating a Route, you can specify...

A.

the order in which the tasks should be completed

B.

the route member who should complete the task

C.

whether the task assignee can delegate the task to someone else

D.

all of these

A potential problem that may prevent the completion of a task or project is called a:

A.

Risk

B.

Issue

C.

Discussion

D.

Dependency

What is TRUE about the Percent Allocation field?

A.

Must total up to 100% for all users

B.

A user can not have over 100% allocation

C.

Must has at least one user assigned with at least 10% allocated

D.

A user can be assigned with 0% (zero percent) allocation

Program Central users can list:

A.

all Programs for their Company

B.

only Programs that they are members of

C.

only Programs that are in the Inactive state

D.

only Programs that are in the Active state

What is a critical path for a project?

A.

It is the sequence of tasks, beginning to end, that takes the longest

B.

It is the sequence of tasks that has the most milestones

C.

It is the path that has the most phase gates

D.

It is the path that takes the shortest sequence time